1106 N SUNSET VALE AVE 90069

Certificate Information: 1106 N SUNSET VALE AVE 90069

Application / Permit
24016-10000-04856
Plan Check / Job No.
B24LA02720
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. INTERIOR AND EXTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING. NEW ROOF DECK.
Permit Issued
Issued on 7/25/2024
Issuing Office
Current Status
Issued on 7/25/2024

Permit Application Status History

Submitted 2/14/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 KEVIN MORALES
Corrections Issued 2/22/2024 KEVIN MORALES
Quality Review Completed 2/22/2024 EUGENE BARBEAU
Applicant returned to address corrections 5/21/2024 KEVIN MORALES
Applicant returned to address corrections 7/9/2024 KEVIN MORALES
Plan Check Approved 7/25/2024 KEVIN MORALES
Issued 7/25/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/9/2024 KEVIN AVILA
Sewer availability Cleared 3/9/2024 KEVIN AVILA
Distance to fire station Cleared 6/15/2024 JOHN CONNEALLY
Grading Pre-Inspection Cleared 7/3/2024 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 7/8/2024 AMBER CAMPBELL
Hydrant and Access approval Cleared 7/24/2024 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

BUILDING-Rough-Frame 6/9/2026   
Gas Test 6/9/2026   
PLUMBING-Rough 6/9/2026   

Inspection Request History

Footing/Foundation/Slab 9/9/2024 Partial Approval HAMIK HARTOUNIAN
Pre-Inspection 9/11/2024 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/9/2025 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Partial Approval BRENDAN MORELLI
Wood Frame 11/4/2025 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 1/8/2026 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 1/8/2026 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 1/27/2026 Partial Approval DAVID WILLIAMS
Interior/Exterior Lathing 1/27/2026 Approved DAVID WILLIAMS
Drywall Nailing 2/13/2026 Partial Approval DAVID WILLIAMS