2845-2847 1/4 N MARSH ST 90039
Certificate Information: 2845-2847 1/4 N MARSH ST 90039
- Application / Permit
- 24016-10000-04830
- Plan Check / Job No.
- B24LA02694
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan. Conversion of (E) recreation room into attached ADU per State Law. No change to building footprint, no change in floor area, no change to exterior facade. NFPA 13D FIRE SPRINKLER THROUGHOUT
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Current Status
- CofO Issued on 3/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2024 | KHUONG TRUONG |
| Corrections Issued | 2/25/2024 | KHUONG TRUONG |
| Applicant returned to address corrections | 5/14/2024 | KHUONG TRUONG |
| Applicant returned to address corrections | 12/24/2024 | ALEXANDER JOO |
| Plan Check Approved | 1/4/2025 | ALEXANDER JOO |
| Issued | 1/14/2025 | APPLICANT |
| CofO in Progress | 3/21/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/21/2025 | DEROLD HAUFF |
| CofO Issued | 3/21/2025 | DEROLD HAUFF |
| Permit Finaled | 3/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 3/5/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2024 | TREVOR QUAN |
| ZI | Cleared | 3/26/2024 | JAZMIN ROQUE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/24/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/24/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/24/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 1/24/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/29/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Pre-Inspection | 1/29/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Interior/Exterior Lathing | 1/31/2025 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Drywall Nailing | 2/5/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 2/5/2025 | Partial Approval | JOSH MEISTER |
| Final | 3/20/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/20/2025 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 3/20/2025 | Approved | HAMIK HARTOUNIAN |