19620 W HAYNES ST 91335
Certificate Information: 19620 W HAYNES ST 91335
- Application / Permit
- 24016-10000-04816
- Plan Check / Job No.
- B24LA02679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached 2-car garage into ADU per GSC 6585.2(e)(1)(A). Work per WFPP.
- Permit Issued
- Issued on 6/27/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | HUAN LE |
| Corrections Issued | 2/19/2024 | HUAN LE |
| Building Plans Picked Up | 2/21/2024 | APPLICANT |
| Applicant returned to address corrections | 5/20/2024 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 6/26/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 6/27/2024 | JOHN MESIAS |
| Issued | 6/27/2024 | APPLICANT |
| CofO in Progress | 9/23/2024 | TROY SANDERS |
| Permit Finaled | 10/2/2024 | JOHN JANSON |
| CofO Issued | 10/2/2024 | JOHN JANSON |
| Permit Finaled | 10/2/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/23/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/23/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 6/25/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/25/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Cavalier Builders Inc; Lic. No.: 758563-B | 6520 PLATT AVE #732 WEST HILLS, CA 91307 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 7/2/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/2/2024 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 7/2/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/22/2024 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/22/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 7/22/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 7/22/2024 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/22/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/24/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 7/24/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/2/2024 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 8/2/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 8/12/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 8/12/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 9/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 9/12/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 9/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 9/12/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 9/12/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 9/12/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 9/20/2024 | Approved | TROY SANDERS |
| Final | 9/20/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 9/20/2024 | Approved | TROY SANDERS |
| HVAC-Final | 9/20/2024 | Approved | TROY SANDERS |
| PLUMBING-Final | 9/20/2024 | Approved | TROY SANDERS |