19620 W HAYNES ST 91335

Certificate Information: 19620 W HAYNES ST 91335

Application / Permit
24016-10000-04816
Plan Check / Job No.
B24LA02679
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached 2-car garage into ADU per GSC 6585.2(e)(1)(A). Work per WFPP.
Permit Issued
Issued on 6/27/2024
Issuing Office
Metro
Current Status
CofO Issued on 10/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 HUAN LE
Corrections Issued 2/19/2024 HUAN LE
Building Plans Picked Up 2/21/2024 APPLICANT
Applicant returned to address corrections 5/20/2024 JOSEPH RAFOLS
Applicant returned to address corrections 6/26/2024 NEHEMIAS RAMOS
Plan Check Approved 6/27/2024 JOHN MESIAS
Issued 6/27/2024 APPLICANT
CofO in Progress 9/23/2024 TROY SANDERS
Permit Finaled 10/2/2024 JOHN JANSON
CofO Issued 10/2/2024 JOHN JANSON
Permit Finaled 10/2/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/23/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/23/2024 EDGAR ALCARAZ
Sewer availability Cleared 2/23/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/24/2024 EDGAR ALCARAZ
Construction near power lines Cleared 6/25/2024 RIDWAN HARDY
Construction within easement Cleared 6/25/2024 RIDWAN HARDY

Contact Information

Contractor Cavalier Builders Inc; Lic. No.: 758563-B 6520 PLATT AVE #732      WEST HILLS, CA 91307

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 7/2/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 7/2/2024 Partial Approval ARUTYUN MADATYAN
Sewer 7/2/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/22/2024 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 7/22/2024 Approved ARUTYUN MADATYAN
Green Building Rough 7/22/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 7/22/2024 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 7/22/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 7/24/2024 Approved ARUTYUN MADATYAN
Insulation 7/24/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 8/2/2024 Partial Approval ARUTYUN MADATYAN
Shower Pan 8/2/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 8/12/2024 Approved ARUTYUN MADATYAN
Green Building Rough 8/12/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 9/12/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 9/12/2024 Not Ready for Inspection ARUTYUN MADATYAN
Final 9/12/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 9/12/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 9/12/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 9/12/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 9/12/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 9/20/2024 Approved TROY SANDERS
Final 9/20/2024 OK to Issue CofO TROY SANDERS
Green Building Final 9/20/2024 Approved TROY SANDERS
HVAC-Final 9/20/2024 Approved TROY SANDERS
PLUMBING-Final 9/20/2024 Approved TROY SANDERS