11201 S ALVARO ST 90059

Certificate Information: 11201 S ALVARO ST 90059

Application / Permit
24016-10000-04732
Plan Check / Job No.
B24LA02622
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLan. REPAIR (E) SFD DUE TO FIRE DAMAGE. REPLACE (E) ROOF WITH NEW TRUSSES. fire sprinklers NFPA 13D is required.
Permit Issued
Issued on 5/13/2024
Issuing Office
Current Status
Permit Finaled on 4/23/2025

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/13/2024 ALFREDO JARA
Corrections Issued 2/14/2024 ALFREDO JARA
Plan Check Approved 3/4/2024 ALFREDO JARA
Issued 5/13/2024 APPLICANT
Permit Finaled 4/8/2025 GABRIEL HERRERA
CofO in Progress 4/23/2025 HAGOP BADOSSIAN
No Progress 4/23/2025 HAGOP BADOSSIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/29/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 2/29/2024 JUSTIN BICOL

Contact Information

Contractor Allied Restoration Services Inc; Lic. No.: 908870-B 3120 E GARVEY AVE S      WEST COVINA, CA 91791
Engineer Ionescu,, Benjamin; Lic. No.: C65482 15375 BARRANCA PARKWAY STE B-205      IRVINE, CA 92618
Engineer Ionescu,, Benjamin; Lic. No.: NA65482       ,
Engineer Zhao,, Xiaoming; Lic. No.: C70068 13402 PARK DR      CERRITOS, CA 90703

Inspector Information

EDMUND LUM, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
LUCIANO GAUNA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
JAIME RIOS, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
ANDEY CHAPARRO, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
RYAN BARNES, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
PATRICK LIEBREGT, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GLEN RAND, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
SHAWN ESHBACH, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GABRIEL HERRERA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/14/2024 Conditional Approval GABRIEL HERRERA
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Approved GABRIEL HERRERA
BUILDING-Rough-Frame 10/30/2024 Approved GABRIEL HERRERA
ELECTRICAL-Rough 10/30/2024 Approved GABRIEL HERRERA
PLUMBING-Rough 10/30/2024 Approved GABRIEL HERRERA
Drywall Nailing 12/10/2024 Approved GABRIEL HERRERA
Insulation 12/10/2024 Approved GABRIEL HERRERA
Interior/Exterior Lathing 12/10/2024 Approved GABRIEL HERRERA
Interior/Exterior Lathing 2/14/2025 Approved GABRIEL HERRERA
Service/Power Release 2/14/2025 Approved GABRIEL HERRERA
Final 4/8/2025 Permit Finaled GABRIEL HERRERA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved GABRIEL HERRERA
Smoke Detectors 4/8/2025 Approved GABRIEL HERRERA