313-315 W 90TH ST 90003

Certificate Information: 313-315 W 90TH ST 90003

Application / Permit
24016-10000-04578
Plan Check / Job No.
B24LA02529
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
convert (E) garage to 1-story detached ADU per GCS 65852.2(e)(1)(A) R3 occupancy. All work per WFPP
Permit Issued
Issued on 7/22/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 KELVIN CHUONG
Corrections Issued 2/20/2024 KELVIN CHUONG
Building Plans Picked Up 2/26/2024 APPLICANT
Plan Check Approved 7/22/2024 JOHN MESIAS
Issued 7/22/2024 APPLICANT
CofO in Progress 4/9/2025 JOHN QUINTANILLA
Permit Finaled 4/13/2025 DEROLD HAUFF
CofO Issued 4/13/2025 DEROLD HAUFF
Permit Finaled 4/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/1/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 5/1/2024 TREVOR QUAN
Sewer availability Cleared 5/1/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/2/2024 TREVOR QUAN
Historic Resource Verification Cleared 5/22/2024 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 5/22/2024 ELIZABETH GALLARDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2024 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 9/27/2024 Partial Approval MICHAEL LEWIS
Pre-Inspection 9/27/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/3/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 10/3/2024 Not Ready for Inspection SABAS ALONSO
Sewer 10/3/2024 Partial Inspection SABAS ALONSO
Underground Mechanical 10/3/2024 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 10/7/2024 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 10/7/2024 Not Ready for Inspection CRAIG DAVIS
Sewer 10/7/2024 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 10/10/2024 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 10/10/2024 Not Ready for Inspection SABAS ALONSO
Sewer 10/10/2024 Approved SABAS ALONSO
Deputy Drilled-In Anchors 10/16/2024 Conditional Approval ALEX COLIN
Excavation/Setback/Form/Re-Bar 10/17/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/17/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/12/2024 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 11/12/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 11/19/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved MICHAEL LEWIS
HVAC-Rough 11/19/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/19/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 11/19/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/21/2024 Approved MICHAEL LEWIS
Green Building Rough 11/21/2024 Approved MICHAEL LEWIS
MERV13>=Rough 11/21/2024 Approved MICHAEL LEWIS
Drywall Nailing 11/26/2024 Approved JOSH MEISTER
Insulation 11/26/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 12/2/2024 Approved ANTHONY RAMOS
Service/Power Release 1/27/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Final 2/25/2025 Approved JOHN QUINTANILLA
Service/Power Release 2/28/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 4/8/2025 Approved JOHN QUINTANILLA
Final 4/8/2025 OK to Issue CofO JOHN QUINTANILLA
Green Building Final 4/8/2025 Approved JOHN QUINTANILLA
HVAC-Final 4/8/2025 Approved JOHN QUINTANILLA
MERV13>=Final 4/8/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 4/8/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Not Required JOHN QUINTANILLA
Smoke Detectors 4/8/2025 Approved JOHN QUINTANILLA