4969 E TWINING ST 90032
Certificate Information: 4969 E TWINING ST 90032
- Application / Permit
- 24016-10000-04282
- Plan Check / Job No.
- B24LA02472
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING . KITCHEN & BATHROOM REMODELING . REMOVING A NON-BEARING WALL TO CREATE A NEW BEDROOM . ** SEE PLAN CHECK COMMENTS**
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/8/2024
Permit Application Status History
| Submitted | 2/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | GEORGE ALVAREZ |
| Corrections Issued | 2/9/2024 | GEORGE ALVAREZ |
| Plan Check Approved | 2/23/2024 | YAQUB MIRZA |
| Issued | 2/23/2024 | APPLICANT |
| Permit Finaled | 11/7/2024 | LILIANA PORTILLO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/22/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/28/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 3/28/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Gas Test | 3/28/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 3/28/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/4/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Gas Test | 4/4/2024 | No Access for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 4/4/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Sewer | 4/4/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Gas Test | 4/9/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 4/9/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/22/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 4/22/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/22/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Sewer | 4/22/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/24/2024 | Corrections Issued | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 4/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 5/6/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 6/10/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 6/10/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/10/2024 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 6/24/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/24/2024 | Approved | LILIANA PORTILLO |
| Final | 9/9/2024 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 9/9/2024 | Approved | LILIANA PORTILLO |
| Final | 10/29/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Final | 11/7/2024 | Permit Finaled | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 11/7/2024 | Approved | LILIANA PORTILLO |