2717 W 70TH ST 90043
Certificate Information: 2717 W 70TH ST 90043
- Application / Permit
- 24016-10000-04151
- Plan Check / Job No.
- B24LA02375
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Detached Garage Conversion to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/1/2024
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2024 | EDWIN ESPIN |
| Corrections Issued | 2/14/2024 | EDWIN ESPIN |
| Plan Check Approved | 3/26/2024 | EDWIN ESPIN |
| Issued | 4/1/2024 | APPLICANT |
| CofO in Progress | 8/9/2024 | JOSE MACIAS |
| Permit Finaled | 9/12/2024 | RUBEN SALAS |
| CofO Issued | 9/12/2024 | RUBEN SALAS |
| Permit Finaled | 9/12/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 3/7/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/20/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 5/28/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 5/28/2024 | Not Ready for Inspection | JOSE MACIAS |
| Underground Mechanical | 5/28/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 5/30/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/30/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/13/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 6/13/2024 | Approved | JOSE MACIAS |
| Gas Test | 6/13/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 6/13/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 6/13/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 6/13/2024 | Approved | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 6/13/2024 | Corrections Issued | JOSE MACIAS |
| Wood Frame | 6/13/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/17/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 6/17/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 6/17/2024 | Approved | JOSE MACIAS |
| Insulation | 6/18/2024 | Not Ready for Inspection | JOSH MEISTER |
| Insulation | 6/20/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/20/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 6/24/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/24/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | JOSH MEISTER |
| Underground Mechanical | 7/18/2024 | Partial Approval | JOSH MEISTER |
| Green Building Final | 7/22/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 7/22/2024 | Approved | JOSE MACIAS |
| Sewer | 7/22/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 7/22/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/25/2024 | Approved | JOSE MACIAS |
| Final | 7/25/2024 | Corrections Issued | JOSE MACIAS |
| Smoke Detectors | 7/25/2024 | Approved | JOSE MACIAS |
| Final | 7/30/2024 | Conditional Approval | JOSE MACIAS |
| Final | 8/9/2024 | OK to Issue CofO | JOSE MACIAS |