1301 N GLENDALE BLVD 90026

Certificate Information: 1301 N GLENDALE BLVD 90026

Application / Permit
24016-10000-04032
Plan Check / Job No.
B24LA02297
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
EPLAN***PROPOSED ALTERATION TO (E) RESTAURANT; WORK TO INCLUDE NEW ROOF, ROOFTOP EQUIPMENT, REMOVE/REPLACE WALLS
Permit Issued
Issued on 8/22/2024
Issuing Office
Current Status
Permit Finaled on 5/28/2025

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 SINA KHOSRAVI
Assigned to Zoning Architect 2/15/2024 SINA KHOSRAVI
Corrections Issued 2/20/2024 SINA KHOSRAVI
Quality Review Completed 3/6/2024 GARO TELMI
Applicant returned to address corrections 5/14/2024 SINA KHOSRAVI
Plan Check Approved 6/18/2024 SINA KHOSRAVI
Issued 8/22/2024 APPLICANT
Permit Finaled 5/27/2025 LUIS CCAMACHO

Permit Application Clearance Information

"Q" conditions Cleared 3/5/2024 DALIA MOKAYED
Drive Through Cleared 4/3/2024 JOSE CARDENAS
Green Code Cleared 5/2/2024 AARON COSTA
DAS Clearance Cleared 5/13/2024 Sarkis Harabedian
Food establishment approval Cleared 6/18/2024 LACDHS APPROVED
Zoning Plan Check Cleared 6/18/2024 Sarkis Harabedian

Contact Information

Architect Liederman,, Jeffrey Steven; Lic. No.: NA29534       ,
Contractor Miller K Z Construction Inc; Lic. No.: 1011565-B       ,
Engineer Allen,, Thomas Christopher; Lic. No.: NA5460       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/29/2024 Partial Approval ALFREDO LOPEZ
Special/Order Compliance 10/29/2024 Partial Approval ALFREDO LOPEZ
Footing/Foundation/Slab 11/26/2024 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 12/10/2024 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 12/18/2024 Partial Approval RAFAEL CORTES
Wood Frame 1/31/2025 Partial Approval LUIS CCAMACHO
Wood Frame 2/5/2025 Partial Approval RAFAEL CORTES
Insulation 2/7/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 2/14/2025 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 2/18/2025 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 3/13/2025 Not Ready for Inspection RONALD JIMENEZ
Partition/T-Bar Ceiling 3/14/2025 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 3/17/2025 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 3/19/2025 Partial Approval LUIS CCAMACHO
Special/Order Compliance 4/11/2025 Partial Approval RAFAEL CORTES
Final 5/20/2025 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 5/20/2025 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 5/20/2025 Approved LUIS CCAMACHO
Final 5/27/2025 Permit Finaled LUIS CCAMACHO