3847 N DRYSDALE AVE 90032

Certificate Information: 3847 N DRYSDALE AVE 90032

Application / Permit
24016-10000-04031
Plan Check / Job No.
B24LA02294
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
E-PLAN. INTERIOR REMODEL TO (E) SFD.
Permit Issued
Issued on 3/12/2024
Issuing Office
Current Status
Permit Finaled on 11/17/2025

Permit Application Status History

Submitted 2/11/2024 APPLICANT
Assigned to Plan Check Engineer 2/12/2024 AMY GUEVARRA
Corrections Issued 2/14/2024 AMY GUEVARRA
Applicant returned to address corrections 2/23/2024 DAVID CASTILLO
Plan Check Approved 3/11/2024 DAVID CASTILLO
Issued 3/12/2024 APPLICANT
Permit Finaled 11/14/2025 LILIANA PORTILLO

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/6/2024 LANNY MERRICK

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/26/2024 Corrections Issued LILIANA PORTILLO
Pre-Inspection 9/19/2024 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 9/23/2024 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/20/2024 Not Ready for Inspection ANTHONY RAMOS
Footing/Foundation/Slab 12/24/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 1/13/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 1/13/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 1/13/2025 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 1/22/2025 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 1/22/2025 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 2/10/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 2/10/2025 Approved LILIANA PORTILLO
Footing/Foundation/Slab 2/10/2025 Approved LILIANA PORTILLO
HVAC-Rough 2/10/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 2/10/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 2/14/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/14/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 2/25/2025 Approved LILIANA PORTILLO
HVAC-Rough 2/25/2025 Conditional Approval LILIANA PORTILLO
PLUMBING-Rough 2/25/2025 Approved LILIANA PORTILLO
Insulation 3/4/2025 Approved LILIANA PORTILLO
Drywall Nailing 3/14/2025 Approved LILIANA PORTILLO
Service/Power Release 3/14/2025 Corrections Issued LILIANA PORTILLO
Service/Power Release 4/1/2025 Approved LILIANA PORTILLO
Shower Pan 4/1/2025 Not Ready for Inspection LILIANA PORTILLO
Shower Pan 4/3/2025 Approved LILIANA PORTILLO
Final 5/14/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 5/14/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 5/14/2025 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 7/3/2025 Corrections Issued LILIANA PORTILLO
Final 8/18/2025 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 8/18/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 8/18/2025 Approved BRENDAN MORELLI
Final 10/24/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Not Ready LILIANA PORTILLO
Final 11/3/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Not Ready LILIANA PORTILLO
Final 11/14/2025 Permit Finaled LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Approved LILIANA PORTILLO