TI TO (E) SOUND STAGE . BUILD OUT OFFICES ON 2ND FLOOR
Permit Issued
Issued on 4/24/2025
Issuing Office
Current Status
Permit Finaled on 1/26/2026

Permit Application Status History

Submitted 2/8/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 HERNAN ARREOLA
Corrections Issued 2/20/2024 HERNAN ARREOLA
Quality Review Completed 2/22/2024 PETER KIM
Assigned to Zoning Architect 2/28/2024 HERNAN ARREOLA
Applicant returned to address corrections 3/8/2024 HERNAN ARREOLA
Plan Check Approved 5/29/2024 HERNAN ARREOLA
Issued 4/24/2025 APPLICANT
Permit Finaled 1/23/2026 LUIS CCAMACHO

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 4/10/2024 FIRE DEPARTMENT
Green Code Cleared 4/11/2024 Lawrence Quirante
DAS Clearance Cleared 4/17/2024 Lawrence Quirante
Zoning Plan Check Cleared 4/24/2024 HERNAN ARREOLA

Contact Information

Architect Wilder,, Arthur J; Lic. No.: C27915 1708 N ALEXANDRIA AVE      LOS ANGELES, CA 90027
Contractor Kprs Construction Services Inc; Lic. No.: 751130-B       ,
Contractor Kprs Construction Services Llc; Lic. No.: 751130-B       ,
Engineer Toranzo,, Luis; Lic. No.: S6014 12005 ALBERS ST 222      VALLEY VILLAGE, CA 91607

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/24/2025 Partial Inspection LUIS CCAMACHO
Footing/Foundation/Slab 9/2/2025 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 9/12/2025 Partial Approval LUIS CCAMACHO
Wall Anchors 10/6/2025 Partial Inspection LUIS CCAMACHO
Light Gage Steel Frame 10/15/2025 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 10/16/2025 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 10/22/2025 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 10/22/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 10/29/2025 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 10/29/2025 Partial Approval LUIS CCAMACHO
Insulation 11/6/2025 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 11/6/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 11/13/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 11/19/2025 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 11/19/2025 Partial Approval LUIS CCAMACHO
Final 12/31/2025 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 12/31/2025 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 12/31/2025 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 12/31/2025 Not Ready for Inspection LUIS CCAMACHO
Final 1/8/2026 Partial Inspection LUIS CCAMACHO
Green Building Final 1/8/2026 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 1/8/2026 Approved LUIS CCAMACHO
Final 1/23/2026 Permit Finaled LUIS CCAMACHO