3904 1/2 S ROXTON AVE 90008

Certificate Information: 3904 1/2 S ROXTON AVE 90008

Application / Permit
24016-10000-03643
Plan Check / Job No.
B24LA02097
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER
Permit Issued
Issued on 3/20/2025
Issuing Office
Current Status
Issued on 3/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/9/2024 DANIEL ABRAMYAN
Corrections Issued 2/10/2024 DANIEL ABRAMYAN
Plan Check Approved 7/2/2024 GIOVANNY CHAVEZ
Issued 3/20/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/28/2024 WALLIE JONG
Sewer availability Cleared 2/28/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/3/2024 WALLIE JONG
Construction within easement Cleared 6/7/2024 RIDWAN HARDY

Contact Information

Contractor Nail & Hammer Construction Corp; Lic. No.: 1053409-B       ,
Engineer Tamu,, O C; Lic. No.: C29787 P O BOX 17083      LONG BEACH, CA 90807
Engineer Tamu,, O C; Lic. No.: NA29787       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/27/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 3/27/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 4/24/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 6/4/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Partial Approval LUIS CASTRO
HVAC-Rough 6/4/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 6/4/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval LUIS CASTRO
Sewer 7/2/2025 Partial Approval ANTHONY RAMOS
ELECTRICAL-Rough 7/24/2025 Approved LUIS CASTRO
HVAC-Rough 7/24/2025 Partial Approval LUIS CASTRO
Insulation 7/24/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 7/24/2025 Approved LUIS CASTRO
Sewer 7/24/2025 Approved LUIS CASTRO
Underground Mechanical 7/24/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 1/8/2026 Approved LUIS CASTRO
Drywall Nailing 1/8/2026 Approved LUIS CASTRO
Green Building Rough 1/8/2026 Approved LUIS CASTRO
Insulation 1/8/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 1/23/2026 Approved LUIS CASTRO
Shower Pan 1/23/2026 Approved LUIS CASTRO
ELECTRICAL-Final 4/3/2026 Not Ready for Inspection LUIS CASTRO
Underground Mechanical 4/3/2026 Corrections Issued LUIS CASTRO