4326 S GRAND VIEW BLVD 90066
Certificate Information: 4326 S GRAND VIEW BLVD 90066
- Application / Permit
- 24016-10000-03565
- Plan Check / Job No.
- B24LA02042
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) PER DESIGN
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2024 | ALFRED RAMIREZ |
| Corrections Issued | 2/8/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 6/11/2024 | KHUONG TRUONG |
| Plan Check Approved | 6/13/2024 | KHUONG TRUONG |
| Issued | 8/28/2024 | APPLICANT |
| CofO in Progress | 9/5/2025 | WILBER ROSALES |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
| CofO Issued | 9/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2024 | DARIN LAM |
| Sewer availability | Cleared | 2/8/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2024 | DARIN LAM |
| Specific Plan | Cleared | 4/4/2024 | JOSHUA JONES |
Contact Information
| Architect | Verdugo,, Emilio Amado; Lic. No.: NA33263 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/18/2024 | Partial Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 9/19/2024 | Corrections Issued | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 10/2/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/2/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/15/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 11/1/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 11/1/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 12/5/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 12/5/2024 | Approved | JESUS PINEDA |
| Sewer | 12/5/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 4/16/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 4/16/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 4/16/2025 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 8/5/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 8/5/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 8/5/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Drywall Nailing | 8/13/2025 | Partial Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 8/13/2025 | Approved | WILBER ROSALES |
| Final | 8/13/2025 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 8/13/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 8/13/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Final | 8/13/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 8/13/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 9/4/2025 | Approved | WILBER ROSALES |
| Final | 9/4/2025 | OK to Issue CofO | WILBER ROSALES |
| HVAC-Final | 9/4/2025 | Approved | WILBER ROSALES |