7315 W 82ND ST 90045

Certificate Information: 7315 W 82ND ST 90045

Application / Permit
24016-10000-03539
Plan Check / Job No.
B24LA02010
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. HELICAL PILE INSTALLATION IS VOLUNTARILY TO PREVENT FURTHER SUBSIDENCE OF THE STRUCTURE. INSTALLATIONS ARE SUBGRADE AND DO NOT AFFECT THE EXTERIOR APPEARANCE OF THE STRUCTURE. INTERIOR CRAWLSPACE POSTS TO BE REPLACED IN KIND AS REQUIRED.
Permit Issued
Issued on 5/24/2024
Issuing Office
Current Status
Permit Finaled on 11/12/2024

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 MAHNAZ NOURHASHEMI
Corrections Issued 2/17/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 2/29/2024 TU HUA
Applicant returned to address corrections 5/19/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 5/24/2024 MAHNAZ NOURHASHEMI
Issued 5/24/2024 APPLICANT
Permit Finaled 11/8/2024 TEMISTOCLES CAAL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/3/2024 SERGIO VALENZUELA

Contact Information

Contractor Dalinghaus Construction Inc; Lic. No.: 983851-B       ,
Engineer Jambhulkar,, Mohan; Lic. No.: C72609 FLAT B-102 NINE HILLS SOCIETY   NIBM ROAD MOHAMMAD WADI PUNE    MAHARASHTRA, 411060

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 7/19/2024 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 7/24/2024 Not Ready for Inspection BOBBY KEY
Special/Order Compliance 7/25/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 8/5/2024 Corrections Issued BOBBY KEY
Final 10/24/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 10/24/2024 Approved BOBBY KEY
Smoke Detectors 10/24/2024 Approved BOBBY KEY
Final 11/8/2024 Permit Finaled TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved TEMISTOCLES CAAL