6764 W HOLLYWOOD BLVD 90028
Certificate Information: 6764 W HOLLYWOOD BLVD 90028
- Application / Permit
- 24016-10000-03537
- Plan Check / Job No.
- B24LA02007
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Amusement Building
- Work Description
- Change of use from Museum to Special Amusement Area (Commerical Exhibits) and TI Tenant Improvement to exiting museum. Includes new Maze Exhibits, new elevators located at the North side of the building, removal of existing rear elevator, infill of existing center stairway, and (2) new toilet rooms.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO Issued on 4/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 2/15/2024 | HERNAN ARREOLA |
| Corrections Issued | 2/26/2024 | HERNAN ARREOLA |
| Quality Review Completed | 2/27/2024 | PETER KIM |
| Applicant returned to address corrections | 4/11/2024 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/25/2024 | HERNAN ARREOLA |
| Plan Check Approved | 6/3/2024 | HERNAN ARREOLA |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 4/4/2025 | TIMOTHY POWELL |
| CofO in Progress | 4/4/2025 | TIMOTHY POWELL |
| CofO in Progress | 4/4/2025 | TIMOTHY POWELL |
| CofO in Progress | 4/4/2025 | TIMOTHY POWELL |
| Permit Finaled | 4/4/2025 | ERNESTO CORRAL |
| CofO Issued | 4/4/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/1/2024 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 3/1/2024 | LAMBERT GIESSINGER |
| Sewer availability | Cleared | 3/5/2024 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2024 | ARNULFO CHAMU |
| Redevelopment Project Area | Cleared | 3/22/2024 | YASMINE BASHIRI |
| Green Code | Cleared | 4/11/2024 | AARON COSTA |
| Fire Marshal Fire Life Safety | Cleared | 4/19/2024 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 4/25/2024 | Fernando Flores |
| Zoning Plan Check | Cleared | 6/3/2024 | Fernando Flores |
Contact Information
| Architect | Loomis,, John C; Lic. No.: NA8684 | , |
| Contractor | Ramirez Ricky; Lic. No.: 800586-B | , |
| Engineer | Chen,, Jeff Ying-Chih; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/24/2024 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 7/2/2024 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 7/8/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 7/11/2024 | Partial Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 7/11/2024 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 7/17/2024 | Partial Approval | TIMOTHY POWELL |
| Structural Steel Frame | 7/17/2024 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 7/22/2024 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 7/29/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 8/7/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 8/16/2024 | Partial Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 8/28/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 9/9/2024 | Partial Approval | TIMOTHY POWELL |
| Insulation | 10/2/2024 | Partial Inspection | TIMOTHY POWELL |
| Masonry Wall/Backfill | 10/2/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 10/11/2024 | Partial Inspection | TIMOTHY POWELL |
| Drywall Nailing | 10/18/2024 | Partial Approval | TIMOTHY POWELL |
| Special/Order Compliance | 10/29/2024 | Approved | TIMOTHY POWELL |
| Structural Steel Frame | 10/29/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 10/30/2024 | Partial Inspection | TIMOTHY POWELL |
| Drywall Nailing | 10/31/2024 | Partial Inspection | TIMOTHY POWELL |
| Drywall Nailing | 12/6/2024 | Partial Approval | TIMOTHY POWELL |
| Special/Order Compliance | 12/20/2024 | Partial Inspection | TIMOTHY POWELL |
| Final | 4/1/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Final | 4/1/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Rough | 4/1/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Reinforced Masonry Frame | 4/1/2025 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV No Gas | TIMOTHY POWELL |
| Smoke Detectors | 4/1/2025 | Approved | TIMOTHY POWELL |
| Final | 4/4/2025 | OK to Issue CofO | TIMOTHY POWELL |
| Green Building Final | 4/4/2025 | Approved | TIMOTHY POWELL |
| Green Building Rough | 4/4/2025 | Approved | TIMOTHY POWELL |
| Reinforced Masonry Frame | 4/4/2025 | Approved | TIMOTHY POWELL |