5510 W PICO BLVD 90019
Certificate Information: 5510 W PICO BLVD 90019
- Application / Permit
- 24016-10000-03501
- Plan Check / Job No.
- B24LA01992
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ***EPLAN*** New tenant improvement and change of use from auto body repair building to a food hall and convert parking lot to dining area. 1 of 2
- Permit Issued
- Issued on 7/18/2025
- Issuing Office
- Metro
- Current Status
- Issued on 7/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | TSE MING HUANG |
| Corrections Issued | 3/11/2024 | TSE MING HUANG |
| Quality Review Completed | 3/13/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/2/2025 | TSE MING HUANG |
| Applicant returned to address corrections | 4/9/2025 | TSE MING HUANG |
| Plan Check Approved | 7/8/2025 | TSE MING HUANG |
| Issued | 7/18/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 1/24/2025 | ADRIAN SANCHEZ |
| Green Code | Cleared | 2/4/2025 | AARON COSTA |
| Historic Resource Verification | Cleared | 3/12/2025 | YASMINE BASHIRI |
| Miscellaneous | Cleared | 3/12/2025 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 3/12/2025 | YASMINE BASHIRI |
| ZI | Cleared | 3/12/2025 | YASMINE BASHIRI |
| DAS Clearance | Cleared | 3/17/2025 | TSE MING HUANG |
| Food Service Establishment | Cleared | 4/2/2025 | CRYSTOL BRANDT |
| Food establishment approval | Cleared | 6/30/2025 | LACDHS APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/28/2025 | Conditional Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 8/4/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 9/17/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Rough | 9/17/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 9/17/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 9/17/2025 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 9/22/2025 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 11/6/2025 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 11/17/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Insulation | 1/16/2026 | Partial Approval | IAN BLINN |