1959 N SHENANDOAH ST 90034
Certificate Information: 1959 N SHENANDOAH ST 90034
- Application / Permit
- 24016-10000-03461
- Plan Check / Job No.
- B24LA01962
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN: FIRE DAMAGE REPAIR TO (E) APARTMENT BUILDING. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/13/2025
Permit Application Status History
| Submitted | 2/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 2/8/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/6/2024 | GURUNATH NESARAJAH |
| Issued | 4/22/2024 | APPLICANT |
| Permit Finaled | 4/29/2025 | FARHAD DADBIN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/22/2024 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Cedar Construction & Development Inc; Lic. No.: 554550-B | , |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 7/29/2024 | Conditional Approval | FARHAD DADBIN |
| Wood Frame | 9/10/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 9/19/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 9/23/2024 | Partial Approval | FARHAD DADBIN |
| Insulation | 1/6/2025 | Approved | FARHAD DADBIN |
| Drywall Nailing | 1/14/2025 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 1/22/2025 | Approved | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 1/23/2025 | Conditional Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 2/3/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 4/23/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 4/29/2025 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 4/29/2025 | Approved | FARHAD DADBIN |