4314 S 7TH AVE 90008
Certificate Information: 4314 S 7TH AVE 90008
- Application / Permit
- 24016-10000-03421
- Plan Check / Job No.
- B24LA01931
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN : INT AND EXT. REMODEL OF EXISTING SFD TO ENGLARGE KITCHEN, ADD A BATHROOM AND WINDOW CHANGEOUT. ALL WORK PER WFPP (SEE COMMENT)
- Permit Issued
- Issued on 3/15/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/25/2024
Permit Application Status History
| Submitted | 2/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2024 | KAMYAR EMAMI |
| Corrections Issued | 2/5/2024 | KAMYAR EMAMI |
| Plan Check Approved | 3/15/2024 | MOHAMMAD ESMAILI |
| Issued | 3/15/2024 | APPLICANT |
| Permit Finaled | 6/24/2024 | ANTHONY EGSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Golden Age Builders; Lic. No.: 1040171-B | , |
| Contractor | Golden Age Construction Inc; Lic. No.: 1040171-B | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/3/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/3/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/3/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 4/3/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/5/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/5/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/5/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 4/5/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | JOSH MEISTER |
| Insulation | 4/9/2024 | Approved | JOSH MEISTER |
| Shower Pan | 4/9/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 4/10/2024 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/11/2024 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 4/12/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 6/11/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 6/11/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 6/11/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 6/11/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 6/11/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/24/2024 | Approved | ANTHONY EGSON |
| Final | 6/24/2024 | Permit Finaled | ANTHONY EGSON |
| HVAC-Final | 6/24/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/24/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Approved | ANTHONY EGSON |