13336 W MCCORMICK ST 91401
Certificate Information: 13336 W MCCORMICK ST 91401
- Application / Permit
- 24016-10000-03294
- Plan Check / Job No.
- B24LA01223
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert (E) garage at rear to ADU. DETACHED ADU PER 65852.2(e)(1)(A). TO BE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGH OUT.
- Permit Issued
- Issued on 7/25/2024
- Issuing Office
- Current Status
- CofO Issued on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | ADRIANA LOPEZ |
| Corrections Issued | 1/31/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 2/7/2024 | GARO TELMI |
| Applicant returned to address corrections | 7/10/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 7/24/2024 | ADRIANA LOPEZ |
| Issued | 7/25/2024 | APPLICANT |
| CofO in Progress | 7/10/2025 | MISAEL ESPARZA |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
| CofO Issued | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/13/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/13/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/13/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 3/20/2024 | TOMMY YIN |
| Construction near power lines | Cleared | 6/3/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 6/3/2024 | TINA MIRANDA |
Contact Information
| Contractor | Gt Remodeling Inc; Lic. No.: 1091310-B | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/6/2024 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/11/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/23/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 12/23/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 1/10/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/10/2025 | Approved | KEVIN BERBERYAN |
| Wood Frame | 1/10/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 1/15/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 1/23/2025 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/23/2025 | Approved | JUAN VALENZUELA |
| Final | 5/28/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 5/28/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 5/28/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 6/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 6/16/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 6/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 6/18/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 6/18/2025 | Approved | MISAEL ESPARZA |
| Final | 7/10/2025 | OK to Issue CofO | MISAEL ESPARZA |