2416-2418 N MORENO DR 90039

Certificate Information: 2416-2418 N MORENO DR 90039

Application / Permit
24016-10000-03114
Plan Check / Job No.
B24LA01731
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT CRAWL SPACE OF (E) DUPLEX INTO AN A.D.U. (2416 1/2) PER ORDINANCE
Permit Issued
Issued on 5/31/2024
Issuing Office
Metro
Current Status
CofO Issued on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2024 APPLICANT
Assigned to Plan Check Engineer 2/5/2024 LAWRENCE QUIRANTE
Corrections Issued 2/8/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 2/12/2024 APPLICANT
Applicant returned to address corrections 3/28/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 4/4/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 5/7/2024 ALEXANDER JOO
Plan Check Approved 5/31/2024 FERNANDO FLORES
Issued 5/31/2024 APPLICANT
CofO in Progress 1/27/2025 ENRIQUE MIRELES
Permit Finaled 1/27/2025 DEROLD HAUFF
CofO Issued 1/27/2025 DEROLD HAUFF
Permit Finaled 1/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 2/16/2024 CHRISTINA BRACO
Address approval Cleared 2/21/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 2/21/2024 CHRISTINA BRACO
Grading Pre-Inspection Cleared 3/28/2024 LAWRENCE QUIRANTE
Miscellaneous Cleared 5/20/2024 MATHEW QUAN
Hold Cleared 6/7/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/3/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/10/2024 Approved ENRIQUE MIRELES
Underground Mechanical 8/19/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/4/2024 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 10/4/2024 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 10/4/2024 Approved ENRIQUE MIRELES
Insulation 10/8/2024 Approved ENRIQUE MIRELES
Shower Pan 10/10/2024 Approved ENRIQUE MIRELES
Drywall Nailing 10/28/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/28/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/20/2024 Approved JOSE MACIAS
ELECTRICAL-Final 12/20/2024 Corrections Issued JOSE MACIAS
Final 12/20/2024 Corrections Issued JOSE MACIAS
Green Building Final 12/20/2024 Approved JOSE MACIAS
HVAC-Final 12/20/2024 Approved JOSE MACIAS
PLUMBING-Final 12/20/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 12/20/2024 Approved JOSE MACIAS
ELECTRICAL-Final 12/23/2024 No Access for Inspection ENRIQUE MIRELES
PLUMBING-Final 12/23/2024 No Access for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 1/23/2025 Approved ENRIQUE MIRELES
Final 1/23/2025 OK to Issue CofO ENRIQUE MIRELES
Gas Test 1/23/2025 Approved ENRIQUE MIRELES