2314 N COMMONWEALTH AVE 90027

Certificate Information: 2314 N COMMONWEALTH AVE 90027

Application / Permit
24016-10000-03074
Plan Check / Job No.
B24LA01710
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: INTERIOR REMODEL OF (E) SFD , CHANGING THE ROOF FROM SHINGLES TO RED TILE ROOF, REMODEL FRONT PORCH. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 3/6/2024
Issuing Office
Current Status
Permit Finaled on 4/7/2025

Permit Application Status History

Submitted 1/30/2024 APPLICANT
Assigned to Plan Check Engineer 2/2/2024 MIROOSH KHACHATOORIAN
Corrections Issued 2/5/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/22/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 3/1/2024 MIROOSH KHACHATOORIAN
Issued 3/6/2024 APPLICANT
Permit Finaled 4/4/2025 ENRIQUE MIRELES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/28/2024 MICHAEL TEMPLE

Contact Information

Contractor Campbell Trinidad Design & Building; Lic. No.: 721765-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/4/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/5/2024 Approved ROY SPAULDING
HVAC-Rough 6/13/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/13/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 8/21/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 9/16/2024 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 9/16/2024 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 9/16/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/18/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 9/18/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/20/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/1/2024 Approved ENRIQUE MIRELES
Drywall Nailing 10/21/2024 Approved ENRIQUE MIRELES
Shower Pan 11/12/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/25/2024 Approved ENRIQUE MIRELES
Gas Test 2/26/2025 Approved ENRIQUE MIRELES
Gas Test 2/27/2025 Approved ENRIQUE MIRELES
PLUMBING-Final 3/7/2025 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 3/14/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Final 4/2/2025 Not Ready for Inspection JEFFREY MEAD
Final 4/2/2025 Not Ready for Inspection JEFFREY MEAD
HVAC-Final 4/2/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Approved JEFFREY MEAD
Smoke Detectors 4/2/2025 Approved JEFFREY MEAD
Final 4/4/2025 Permit Finaled ENRIQUE MIRELES