854 S TREMAINE AVE 90005

Certificate Information: 854 S TREMAINE AVE 90005

Application / Permit
24016-10000-03064
Plan Check / Job No.
B24LA01704
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT (317.46 SF) PER CA GOVT. CODE 65852.2(e)(1)(A) AND STORAGE (PANTRY, EXTERIOR ACCESS ONLY) (78.54 SF).
Permit Issued
Issued on 7/31/2024
Issuing Office
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2024 APPLICANT
Assigned to Plan Check Engineer 2/23/2024 GIOVANNY CHAVEZ
Corrections Issued 2/26/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 7/5/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 7/25/2024 GIOVANNY CHAVEZ
Plan Check Approved 7/30/2024 GIOVANNY CHAVEZ
Issued 7/31/2024 APPLICANT
CofO in Progress 1/6/2025 JOSE MACIAS
Permit Finaled 1/9/2025 DEROLD HAUFF
CofO Issued 1/9/2025 DEROLD HAUFF
Permit Finaled 1/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/27/2024 JUSTIN BICOL
Sewer availability Cleared 2/27/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 3/4/2024 JUSTIN BICOL
Construction near power lines Cleared 6/13/2024 RIDWAN HARDY
Roof/Waste drainage to street Cleared 7/10/2024 JUSTIN BICOL

Contact Information

Contractor Viktor Construction & Remodeling; Lic. No.: 1085128-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/2/2024 Partial Inspection RONNIE MINDANAO
PLUMBING-Rough 8/15/2024 Partial Approval RONNIE MINDANAO
Footing/Foundation/Slab 8/21/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 10/4/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 10/4/2024 Corrections Issued RONNIE MINDANAO
Green Building Rough 10/4/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 10/4/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 10/4/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 10/4/2024 Not Ready for Inspection RONNIE MINDANAO
Wood Frame 10/4/2024 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 10/9/2024 Approved RONNIE MINDANAO
ELECTRICAL-Rough 10/9/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Approved RONNIE MINDANAO
Green Building Rough 10/9/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 10/9/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 10/9/2024 Approved RONNIE MINDANAO
Insulation 10/11/2024 Not Ready for Inspection ANTHONY RAMOS
BUILDING-Rough-Frame 10/15/2024 Approved ANTHONY RAMOS
Green Building Rough 10/15/2024 Approved ANTHONY RAMOS
Insulation 10/15/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 10/15/2024 Partial Approval ANTHONY RAMOS
Drywall Nailing 10/22/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 10/22/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Not Ready RONNIE MINDANAO
Final 12/30/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/30/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/30/2024 Approved ENRIQUE MIRELES
Final 1/3/2025 OK to Issue CofO JOSE MACIAS