15557 W DEL GADO PL 91403
Certificate Information: 15557 W DEL GADO PL 91403
- Application / Permit
- 24016-10000-02741
- Plan Check / Job No.
- B24LA01551
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERSION OF SECOND FLOOR ACCESSORY LIVING QUARTERS (1096 SF) ABOVE GARAGE TO NEW DETACHED ADU. ADD NEW KITCHEN. "COMPLY WITH DEPARTMENT ORDER effective date 02/08/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Current Status
- CofO Issued on 9/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2024 | ADAM HEGAZI |
| Corrections Issued | 2/6/2024 | ADAM HEGAZI |
| Plan Check Approved | 2/21/2024 | ADAM HEGAZI |
| Issued | 2/26/2024 | APPLICANT |
| CofO in Progress | 7/31/2024 | ARAM AVAKIAN |
| Permit Finaled | 9/6/2024 | DANIEL SANCHEZ |
| CofO Issued | 9/6/2024 | DANIEL SANCHEZ |
| Permit Finaled | 9/6/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/9/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2024 | COLIN LOREDO |
Contact Information
| Architect | Dunbar,, Laura Kay; Lic. No.: NA24437 | , |
| Contractor | Mvp Builders; Lic. No.: 1009142-B | , |
| Contractor | Mvp Leaders Inc; Lic. No.: 1009142-B | , |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2024 | Approved | ARAM AVAKIAN |
| PLUMBING-Rough | 5/6/2024 | Approved | ARAM AVAKIAN |
| BUILDING-Rough-Frame | 6/3/2024 | Approved | ARAM AVAKIAN |
| Final | 6/3/2024 | OK to Issue CofO | ARAM AVAKIAN |
| MERV13>=Final | 6/3/2024 | Approved | ARAM AVAKIAN |
| MERV13>=Rough | 6/3/2024 | Approved | ARAM AVAKIAN |
| Smoke Detectors | 6/3/2024 | Approved | ARAM AVAKIAN |