8823 W PICO BLVD 90035

Certificate Information: 8823 W PICO BLVD 90035

Application / Permit
24016-10000-02681
Plan Check / Job No.
B24LA01484
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FOR UNIT 8817 FROM RETAIL TO RESTAURANT. COMBINING 8817 WITH 8823(EXISTING TAKE-OUT RESTAURANT) INTO ONE RESTAURANT. CASE MANAGMENT #42645.
Permit Issued
Issued on 5/16/2024
Issuing Office
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 CARLOS MONTES
Assigned to Zoning Architect 2/8/2024 CARLOS MONTES
Corrections Issued 2/13/2024 CARLOS MONTES
Quality Review Completed 2/14/2024 GARO TELMI
Applicant returned to address corrections 4/15/2024 CARLOS MONTES
Plan Check Approved 5/16/2024 CARLOS MONTES
Issued 5/16/2024 APPLICANT
CofO in Progress 11/13/2024 FARHAD DADBIN
Permit Finaled 11/18/2024 DAVID TSAU
CofO Issued 11/18/2024 DAVID TSAU
Permit Finaled 11/18/2024 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 3/4/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/5/2024 CELINA MORENO
Sewer availability Cleared 3/5/2024 CELINA MORENO
Grading Pre-Inspection Cleared 3/19/2024 VASIL MIHALEV
DAS Clearance Cleared 5/16/2024 Fernando Flores
Food establishment approval Cleared 5/16/2024 LACDHS APPROVED
Zoning Plan Check Cleared 5/16/2024 CARLOS MONTES

Contact Information

Contractor Oracle Construction Services Inc; Lic. No.: 1090821-B       ,

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2024 Not Ready for Inspection FARHAD DADBIN
Insulation 6/25/2024 Not Ready for Inspection FARHAD DADBIN
Wood Frame 6/25/2024 Not Ready for Inspection FARHAD DADBIN
Wood Frame 6/28/2024 Conditional Approval FARHAD DADBIN
Drywall Nailing 7/8/2024 Approved FARHAD DADBIN
Final 11/8/2024 Not Ready for Inspection FARHAD DADBIN
METHANE-Final 11/8/2024 Approved FARHAD DADBIN
METHANE-Rough 11/8/2024 Approved FARHAD DADBIN
Reinforced Masonry Frame 11/8/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 11/8/2024 Approved FARHAD DADBIN
Final 11/13/2024 OK to Issue CofO FARHAD DADBIN