7620 S STETSON AVE 90045
Certificate Information: 7620 S STETSON AVE 90045
- Application / Permit
- 24016-10000-02566
- Plan Check / Job No.
- B24LA01403
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- EPLAN. CONVERT DETACHED GARAGE INTO STORAGE BUILDING. REPLACE ROOF FRAMING. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 1/27/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 2/12/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 2/13/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 3/7/2024 | ROSENDO MEDINA |
| Plan Check Approved | 5/3/2024 | ROSENDO MEDINA |
| Issued | 8/22/2024 | APPLICANT |
| Permit Finaled | 7/21/2025 | RICHARD STEINBACH |
| CofO Issued | 7/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/15/2024 | OSCAR CASTRO |
| Specific Plan | Cleared | 5/1/2024 | MOHAMMAD HASAN |
Contact Information
| Contractor | Artisan Build Group; Lic. No.: 1059364-B | , |
| Contractor | Artisan Development Group Inc; Lic. No.: 1059364-B | , |
| Engineer | Bayani-Rad,, Padra; Lic. No.: C86320 | 15901 HAWTHORNE BLVD UNIT 220 LAWNDALE, CA 90260 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/24/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/1/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/21/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/21/2025 | Approved | BOBBY KEY |
| HVAC-Rough | 2/21/2025 | Approved | BOBBY KEY |
| Insulation | 2/21/2025 | Partial Approval | BOBBY KEY |
| Insulation | 3/7/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 3/7/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 3/7/2025 | Partial Approval | RUBEN RIVAS |
| Drywall Nailing | 3/11/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/11/2025 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 7/15/2025 | Approved | RUBEN RIVAS |
| Final | 7/15/2025 | Partial Approval | RUBEN RIVAS |
| HVAC-Final | 7/15/2025 | Approved | RUBEN RIVAS |
| METHANE-Final | 7/15/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 7/15/2025 | Approved | RUBEN RIVAS |