6422 N JAMIESON AVE 91335
Certificate Information: 6422 N JAMIESON AVE 91335
- Application / Permit
- 24016-10000-02439
- Plan Check / Job No.
- B24LA01342
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing detached garage to ADU per CA Govt. Code 65852.2(e)(1)(A). Design per WFPP.
- Permit Issued
- Issued on 2/12/2024
- Issuing Office
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2024 | CAROLEAN BASMA |
| Corrections Issued | 1/27/2024 | CAROLEAN BASMA |
| Plan Check Approved | 2/10/2024 | CAROLEAN BASMA |
| Issued | 2/12/2024 | APPLICANT |
| CofO in Progress | 9/30/2024 | JEFFREY BULL |
| Permit Finaled | 11/15/2024 | JOHN JANSON |
| CofO Issued | 11/15/2024 | JOHN JANSON |
| Permit Finaled | 11/15/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/1/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2024 | CARLOS RAMIREZ |
| ZI | Cleared | 2/2/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/10/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 4/10/2024 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 4/12/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/13/2024 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 5/13/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 5/13/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 5/13/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/21/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 5/21/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 5/21/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/21/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 5/21/2024 | Approved | JEFFREY BULL |
| Insulation | 5/22/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 5/28/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/28/2024 | Approved | JEFFREY BULL |
| Final | 9/17/2024 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 9/17/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 9/17/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 9/17/2024 | Approved | JEFFREY BULL |
| Final | 9/30/2024 | OK to Issue CofO | JEFFREY BULL |