410 N AVENUE 66 90042
Certificate Information: 410 N AVENUE 66 90042
- Application / Permit
- 24016-10000-02424
- Plan Check / Job No.
- B24LA01335
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Remodel (E) Single family dwelling. Per engineering design.
- Permit Issued
- Issued on 3/5/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/27/2024
Permit Application Status History
| Submitted | 1/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2024 | EDWIN ESPIN |
| Corrections Issued | 1/29/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 2/23/2024 | ALFREDO JARA |
| Plan Check Approved | 3/3/2024 | ALFREDO JARA |
| Issued | 3/5/2024 | APPLICANT |
| Permit Finaled | 8/27/2024 | BRENDAN MORELLI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2024 | JEANIE LAM |
| Sewer availability | Cleared | 2/8/2024 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 2/13/2024 | MICHAEL TEMPLE |
| HPOZ | Cleared | 2/20/2024 | MICAELA TORRES-GIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/26/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/11/2024 | Partial Inspection | JOSEPH MCGARRY |
| Wood Frame | 4/11/2024 | Partial Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/22/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 5/10/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/15/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/3/2024 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 7/9/2024 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 7/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 7/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 7/17/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Shower Pan | 7/24/2024 | Approved | JOSH MEISTER |
| Final | 8/21/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/21/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/27/2024 | Approved | BRENDAN MORELLI |
| Final | 8/27/2024 | Permit Finaled | BRENDAN MORELLI |
| HVAC-Final | 8/27/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 8/27/2024 | Approved | BRENDAN MORELLI |