173 1/2 N CITRUS AVE 90036

Certificate Information: 173 1/2 N CITRUS AVE 90036

Application / Permit
24016-10000-02408
Plan Check / Job No.
B24LA01317
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GA GOVT. CODE 65852.2(e)(1)(A). *COMPLY WITH DEPARTMENT ORDER effective date 10/24/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 8/26/2024
Issuing Office
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2024 APPLICANT
Assigned to Plan Check Engineer 1/31/2024 KAMYAR EMAMI
Corrections Issued 2/13/2024 KAMYAR EMAMI
Applicant returned to address corrections 6/27/2024 DANIEL ABRAMYAN
Plan Check Approved 8/8/2024 GIOVANNY CHAVEZ
Issued 8/26/2024 APPLICANT
Permit Finaled 1/27/2026 DANIEL SANCHEZ
CofO Issued 1/27/2026 DANIEL SANCHEZ
Permit Finaled 1/27/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 6/25/2024 CELINA MORENO
Sewer availability Cleared 6/25/2024 CELINA MORENO
Construction near power lines Cleared 8/2/2024 RIDWAN HARDY
Construction within easement Cleared 8/2/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/5/2024 CELINA MORENO

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor Rocka Builders Inc; Lic. No.: 1050219-B       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2024 Approved ROBERT NILES
ELECTRICAL-Rough 2/12/2025 Not Ready for Inspection PETER RUBIO
PLUMBING-Rough 2/12/2025 Not Ready for Inspection PETER RUBIO
Pre-Inspection 2/12/2025 Corrections Issued PETER RUBIO
Footing/Foundation/Slab 6/30/2025 Partial Approval RUBEN PEREZ
BUILDING-Rough-Frame 7/8/2025 Partial Approval RUBEN PEREZ
Green Building Rough 7/8/2025 Not Ready for Inspection RUBEN PEREZ
METHANE-Rough 7/8/2025 Not Ready for Inspection RUBEN PEREZ
Wood Frame 7/8/2025 Not Ready for Inspection RUBEN PEREZ
ELECTRICAL-Rough 7/21/2025 Approved RUBEN PEREZ
Insulation 7/21/2025 Approved RUBEN PEREZ
Drywall Nailing 7/25/2025 Approved RUBEN PEREZ
Green Building Rough 7/25/2025 Approved RUBEN PEREZ
Wood Frame 7/25/2025 Approved RUBEN PEREZ
Footing/Foundation/Slab 8/13/2025 Approved PETER RUBIO
BUILDING-Rough-Frame 8/26/2025 Approved PETER RUBIO
ELECTRICAL-Final 8/26/2025 Corrections Issued PETER RUBIO
Final 8/26/2025 Corrections Issued PETER RUBIO
Green Building Final 8/26/2025 Not Ready for Inspection PETER RUBIO
HVAC-Final 8/26/2025 Approved PETER RUBIO
METHANE-Final 8/26/2025 Approved PETER RUBIO
METHANE-Rough 8/26/2025 Approved PETER RUBIO
PLUMBING-Final 8/26/2025 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Not Required PETER RUBIO
Smoke Detectors 8/26/2025 Approved PETER RUBIO
ELECTRICAL-Final 9/18/2025 Approved PETER RUBIO
Final 9/18/2025 Corrections Issued PETER RUBIO
Green Building Final 9/18/2025 Approved PETER RUBIO
HVAC-Final 9/18/2025 Approved PETER RUBIO
PLUMBING-Final 9/18/2025 Approved PETER RUBIO
Final 10/9/2025 OK to Issue CofO RUBEN PEREZ