249 W 64TH ST 90003
Certificate Information: 249 W 64TH ST 90003
- Application / Permit
- 24016-10000-02379
- Plan Check / Job No.
- B23VN17079
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR ALTERATION TO REMODEL THE BATHROOMS AND KITCHENS. ALTERATION AND REMOVE ALL REQUIRED PARKING FOR BLDG AND SITE PER AB2097. REPLACE WINDOWS AND DOORS. REROOF THE EXISTING ROOF (SEE COMMENTS)
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/2/2026
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | MINA HABIB |
| Corrections Issued | 1/24/2024 | MINA HABIB |
| Quality Review Completed | 1/26/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/11/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/18/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/22/2024 | MINA HABIB |
| Applicant returned to address corrections | 5/3/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/17/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/24/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/25/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/26/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/31/2024 | MINA HABIB |
| Applicant returned to address corrections | 8/9/2024 | MINA HABIB |
| Applicant returned to address corrections | 8/15/2024 | MINA HABIB |
| Plan Check Approved | 8/29/2024 | MINA HABIB |
| Issued | 9/4/2024 | APPLICANT |
| Permit Finaled | 12/31/2025 | JOHN QUINTANILLA |
Permit Application Clearance Information
| ZA Case | Cleared | 2/7/2024 | SPENCER WEJROWSKI |
| Tenant Habitability Plan | Cleared | 2/9/2024 | RICARDO BOHORQUEZ |
| Historic Resource Verification | Cleared | 3/18/2024 | RAFAEL FONTES |
| Address approval | Cleared | 3/20/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 3/20/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 3/20/2024 | JUSTIN BICOL |
| Prkng lot landscape/Water mgmt | Cleared | 3/29/2024 | BRENNEN OBETO |
| Redevelopment Project Area | Cleared | 4/16/2024 | ELIZABETH GALLARDO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2024 | JUSTIN BICOL |
| Green Code | Cleared | 7/26/2024 | MINA HABIB |
| Roof/Waste drainage to street | Cleared | 8/16/2024 | JOSE HERNANDEZ |
Contact Information
| Architect | Musser,, David Charles; Lic. No.: C15234 | 320 E GREENWOOD AVE LA HABRA, CA 90631 |
| Contractor | Precision General Commercial Contractors Inc; Lic. No.: 790153-B | 7250 REDWOOD BLVD STE 214 NOVATO, CA 94945 |
| Engineer | Burica,, Michael Jerome; Lic. No.: C57151 | 9283 RESEARCH DR IRVINE, CA 92618 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Approved | MICHAEL LEWIS |
| Insulation | 12/5/2024 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 12/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/29/2025 | Approved | JOHN QUINTANILLA |
| Final | 12/29/2025 | Partial Inspection | JOHN QUINTANILLA |
| MERV13>=Final | 12/29/2025 | Approved | JOHN QUINTANILLA |
| MERV13>=Rough | 12/29/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 12/29/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 12/29/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Final | 12/31/2025 | Permit Finaled | JOHN QUINTANILLA |
| Smoke Detectors | 12/31/2025 | Approved | JOHN QUINTANILLA |