2447 S PATRICIA AVE 90064

Certificate Information: 2447 S PATRICIA AVE 90064

Application / Permit
24016-10000-02042
Plan Check / Job No.
B24LA01106
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (E) Detached Garage At Rear of the lot to be converted into an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP.
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
Issued on 10/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/26/2024 APPLICANT
Assigned to Plan Check Engineer 1/26/2024 EDWIN ESPIN
Corrections Issued 1/27/2024 EDWIN ESPIN
Applicant returned to address corrections 9/19/2024 CAROLEAN BASMA
Plan Check Approved 10/2/2024 CAROLEAN BASMA
Issued 10/2/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 6/21/2024 RIDWAN HARDY
Construction within easement Cleared 6/21/2024 RIDWAN HARDY
Address approval Cleared 8/27/2024 BRENDEN HAWK
Sewer availability Cleared 8/27/2024 BRENDEN HAWK
ZA Case Cleared 8/27/2024 NATHAN ROMINE
Grading Pre-Inspection Cleared 8/27/2024 VASIL MIHALEV
Specific Plan Cleared 9/13/2024 HAMID GHAEMMAGHAMI
Eng Process Fee Ord 176,300 Cleared 9/15/2024 BRENDEN HAWK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/3/2024 Corrections Issued ASHLEY THOMPSON
Gas Test 10/3/2024 Not Ready for Inspection ASHLEY THOMPSON
Sewer 10/3/2024 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 10/3/2024 Partial Approval REGINA MENDEZ
Footing/Foundation/Slab 10/4/2024 Partial Approval ASHLEY THOMPSON
Special/Order Compliance 10/4/2024 Corrections Issued ASHLEY THOMPSON
Underground Mechanical 10/4/2024 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 10/16/2024 Partial Approval CARLOS MATAMOROS
Gas Test 10/16/2024 Corrections Issued CARLOS MATAMOROS
Green Building Rough 10/16/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 10/16/2024 Corrections Issued CARLOS MATAMOROS
METHANE-Rough 10/16/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/16/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 10/21/2024 Approved KIRK SANDERS
Gas Test 10/21/2024 Approved KIRK SANDERS
HVAC-Rough 10/21/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 10/21/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 10/21/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/25/2024 Approved ASHLEY THOMPSON
Green Building Rough 10/25/2024 Approved ASHLEY THOMPSON
HVAC-Rough 10/25/2024 Approved ASHLEY THOMPSON
Insulation 10/25/2024 Corrections Issued ASHLEY THOMPSON
Shower Pan 10/25/2024 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 10/30/2024 Approved ASHLEY THOMPSON
Shower Pan 10/30/2024 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/1/2024 Approved DANIEL VERA
ELECTRICAL-Final 1/17/2025 Corrections Issued CARLOS MATAMOROS
Final 1/17/2025 Corrections Issued CARLOS MATAMOROS
Green Building Final 1/17/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 1/17/2025 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 1/17/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 1/17/2025 Approved CARLOS MATAMOROS
Final 1/31/2025 Corrections Issued EVAN COOPER
Green Building Final 1/31/2025 Approved EVAN COOPER