1437 W 94TH PL 90047

Certificate Information: 1437 W 94TH PL 90047

Application / Permit
24016-10000-01849
Plan Check / Job No.
B24LA01039
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 2/28/2024
Issuing Office
Current Status
Issued on 2/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/20/2024 APPLICANT
Assigned to Plan Check Engineer 1/23/2024 DANIEL ABRAMYAN
Corrections Issued 1/24/2024 DANIEL ABRAMYAN
Plan Check Approved 2/25/2024 GURUNATH NESARAJAH
Issued 2/28/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/25/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 1/25/2024 CHRISTINA BRACO
Sewer availability Cleared 1/25/2024 CHRISTINA BRACO
Construction near power lines Cleared 2/15/2024 TINA MIRANDA
Construction within easement Cleared 2/15/2024 TINA MIRANDA

Contact Information

Contractor N L M'S Elite Construction Company; Lic. No.: 915160-B       ,
Engineer Chang,, Yeh; Lic. No.: S6868 168 S SIERRA MADRE BLVD 109      PASADENA, CA 91107

Inspector Information

RAUL BARAJAS, (213) 202-3211 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/29/2024 Corrections Issued JOSE MACIAS
Excavation/Setback/Form/Re-Bar 3/29/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 3/29/2024 Corrections Issued JOSE MACIAS
HVAC-Rough 3/29/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 3/29/2024 Corrections Issued JOSE MACIAS
Deputy Drilled-In Anchors 6/11/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 7/2/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 12/2/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 12/4/2024 Approved JOSE MACIAS
Underground Mechanical 12/4/2024 Approved JOSE MACIAS
Pre-Inspection 1/14/2025 Approved MICHAEL LEWIS
Footing/Foundation/Slab 1/28/2025 Partial Inspection JOHN QUINTANILLA
PLUMBING-Final 8/14/2025 Not Ready for Inspection WAYNE REGESTER
Underground Mechanical 8/14/2025 Partial Approval WAYNE REGESTER
ELECTRICAL-Rough 10/29/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 11/6/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 11/6/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 11/6/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 12/31/2025 Partial Approval ANTHONY RAMOS
Underground Mechanical 12/31/2025 Partial Approval ANTHONY RAMOS
PLUMBING-Rough 1/14/2026 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 1/14/2026 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 2/9/2026 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 2/9/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 2/27/2026 Conditional Approval MICHAEL LEWIS
HVAC-Rough 2/27/2026 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 2/27/2026 Approved MICHAEL LEWIS
Deputy Steel/Welding 3/3/2026 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 4/22/2026 Approved MICHAEL LEWIS
HVAC-Rough 4/22/2026 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/18/2026 Approved RAUL BARAJAS