2318-2320 W 39TH ST 90008

Certificate Information: 2318-2320 W 39TH ST 90008

Application / Permit
24016-10000-01714
Plan Check / Job No.
B23LA24020
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: ENCLOSRE COVERED PATIO AND CONVERT PORTION OF (E) DUPLEX TO ATTACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C)
Permit Issued
Issued on 10/25/2024
Issuing Office
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 DANIEL YIP
Corrections Issued 1/18/2024 DANIEL YIP
Quality Review Completed 1/22/2024 GARO TELMI
Applicant returned to address corrections 4/25/2024 DANIEL YIP
Applicant returned to address corrections 6/6/2024 DANIEL YIP
Plan Check Approved 10/24/2024 DANIEL YIP
Issued 10/25/2024 APPLICANT
CofO in Progress 10/21/2025 LUIS CASTRO
Permit Finaled 10/23/2025 DEROLD HAUFF
CofO Issued 10/23/2025 DEROLD HAUFF
Permit Finaled 10/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/1/2024 DAVID LOPEZ
Sewer availability Cleared 2/5/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/7/2024 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/14/2024 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 11/14/2024 Approved BARRY HACHE
BUILDING-Rough-Frame 11/25/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 1/17/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 1/17/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 1/17/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 1/17/2025 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 1/31/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 1/31/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved LUIS CASTRO
HVAC-Rough 1/31/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 1/31/2025 Partial Approval LUIS CASTRO
Special/Order Compliance 1/31/2025 Partial Inspection RAUL BARAJAS
Insulation 2/25/2025 Approved ALEX COLIN
Interior/Exterior Lathing 2/25/2025 Approved ALEX COLIN
Shower Pan 2/25/2025 Approved ALEX COLIN
Drywall Nailing 3/27/2025 Approved LUIS CASTRO
Final 8/15/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Final 8/15/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Approved LUIS CASTRO
ELECTRICAL-Final 10/3/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 10/3/2025 Approved LUIS CASTRO
Final 10/3/2025 Corrections Issued LUIS CASTRO
HVAC-Final 10/3/2025 Approved LUIS CASTRO
HVAC-Rough 10/3/2025 Approved LUIS CASTRO
PLUMBING-Rough 10/3/2025 Approved LUIS CASTRO
Smoke Detectors 10/3/2025 Approved LUIS CASTRO
Final 10/20/2025 OK to Issue CofO LUIS CASTRO