324 1/2 W 90TH ST 90003

Certificate Information: 324 1/2 W 90TH ST 90003

Application / Permit
24016-10000-01606
Plan Check / Job No.
B24LA00891
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) 3 car garage into ADU
Permit Issued
Issued on 3/18/2025
Issuing Office
South Los Angeles
Current Status
Issued on 3/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/18/2024 APPLICANT
Assigned to Plan Check Engineer 1/22/2024 JOSE VELAZQUEZ
Corrections Issued 1/23/2024 JOSE VELAZQUEZ
Building Plans Picked Up 1/24/2024 APPLICANT
Plan Check Approved 12/9/2024 ZAW HAN
Issued 3/18/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/24/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 1/25/2024 JUSTIN BICOL
Construction near power lines Cleared 5/10/2024 RIDWAN HARDY
Construction within easement Cleared 5/10/2024 RIDWAN HARDY
Tenant Habitability Plan Cleared 8/8/2024 RICARDO BOHORQUEZ
Address approval Cleared 12/9/2024 JUSTIN BICOL
Hold Cleared 4/24/2025 MARIA VENDIVIL

Contact Information

Contractor J & A Improvements; Lic. No.: 930856-B 7329 SUVA ST #26      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/29/2025 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 5/2/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 5/12/2025 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 5/19/2025 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 6/27/2025 Not Ready for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 6/30/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/8/2025 No Access for Inspection JOHN QUINTANILLA
Green Building Rough 9/8/2025 No Access for Inspection JOHN QUINTANILLA
MERV13>=Rough 9/8/2025 No Access for Inspection JOHN QUINTANILLA
Rough-Elec/Plmb/HVAC 9/10/2025 Partial Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 9/23/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Approved JOHN QUINTANILLA
HVAC-Rough 9/23/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/24/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 9/24/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 9/24/2025 Not Ready for Inspection JOHN QUINTANILLA
MERV13>=Rough 9/24/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 9/24/2025 Not Ready for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 9/30/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 9/30/2025 Approved JOHN QUINTANILLA
Insulation 10/8/2025 Approved JOHN QUINTANILLA
Drywall Nailing 10/27/2025 Approved JOHN QUINTANILLA
Green Building Rough 10/27/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 10/30/2025 Approved JOHN QUINTANILLA
Gas Test 12/15/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 12/15/2025 Not Ready for Inspection JOHN QUINTANILLA
Sewer 12/15/2025 Not Ready for Inspection JOHN QUINTANILLA
Underground Mechanical 12/15/2025 Corrections Issued JOHN QUINTANILLA
Sewer 12/17/2025 Partial Approval SALVADOR MARTINEZ
Underground Mechanical 12/17/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 12/23/2025 Approved JOHN QUINTANILLA