4062 1/2 S 8TH AVE 90008
Certificate Information: 4062 1/2 S 8TH AVE 90008
- Application / Permit
- 24016-10000-01588
- Plan Check / Job No.
- B24LA00874
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached Garage into ADU per state law
- Permit Issued
- Issued on 5/22/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 1/18/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 4/15/2024 | ZAW HAN |
| Plan Check Approved | 5/21/2024 | MINA HABILI |
| Issued | 5/22/2024 | APPLICANT |
| CofO in Progress | 1/28/2025 | RAUL BARAJAS |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| CofO Issued | 2/2/2025 | DEROLD HAUFF |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2024 | ANTHONY TRAN |
| Sewer availability | Cleared | 1/19/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2024 | ANTHONY TRAN |
| Construction near power lines | Cleared | 5/16/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/4/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/4/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 6/4/2024 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/10/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/10/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 6/10/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/11/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/12/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/17/2024 | Approved | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 6/18/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/20/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 6/20/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/24/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/24/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 6/24/2024 | Approved | ANTHONY EGSON |
| Insulation | 6/26/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 6/26/2024 | Partial Approval | JOSH MEISTER |
| Shower Pan | 6/26/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 6/28/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/2/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 8/1/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 8/1/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 8/1/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 8/1/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 8/1/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/28/2025 | Approved | RAUL BARAJAS |
| Final | 1/28/2025 | OK to Issue CofO | RAUL BARAJAS |
| HVAC-Final | 1/28/2025 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 1/28/2025 | Approved | RAUL BARAJAS |