4062 1/2 S 8TH AVE 90008

Certificate Information: 4062 1/2 S 8TH AVE 90008

Application / Permit
24016-10000-01588
Plan Check / Job No.
B24LA00874
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached Garage into ADU per state law
Permit Issued
Issued on 5/22/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2024 APPLICANT
Assigned to Plan Check Engineer 1/18/2024 NEHEMIAS RAMOS
Corrections Issued 1/18/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 4/15/2024 ZAW HAN
Plan Check Approved 5/21/2024 MINA HABILI
Issued 5/22/2024 APPLICANT
CofO in Progress 1/28/2025 RAUL BARAJAS
Permit Finaled 2/2/2025 DEROLD HAUFF
CofO Issued 2/2/2025 DEROLD HAUFF
Permit Finaled 2/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/19/2024 ANTHONY TRAN
Sewer availability Cleared 1/19/2024 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 1/22/2024 ANTHONY TRAN
Construction near power lines Cleared 5/16/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Tamu,, O C; Lic. No.: C29787 P O BOX 17083      LONG BEACH, CA 90807

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/4/2024 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 6/4/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 6/4/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 6/10/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 6/10/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 6/10/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 6/11/2024 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 6/12/2024 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 6/17/2024 Approved ANTHONY EGSON
Deputy Drilled-In Anchors 6/18/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/20/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval ANTHONY EGSON
HVAC-Rough 6/20/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 6/24/2024 Approved ANTHONY EGSON
Green Building Rough 6/24/2024 Approved ANTHONY EGSON
HVAC-Rough 6/24/2024 Approved ANTHONY EGSON
Insulation 6/26/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 6/26/2024 Partial Approval JOSH MEISTER
Shower Pan 6/26/2024 Approved JOSH MEISTER
Drywall Nailing 6/28/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 7/2/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 8/1/2024 Corrections Issued ANTHONY EGSON
Final 8/1/2024 Corrections Issued ANTHONY EGSON
HVAC-Final 8/1/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 8/1/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 8/1/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 1/28/2025 Approved RAUL BARAJAS
Final 1/28/2025 OK to Issue CofO RAUL BARAJAS
HVAC-Final 1/28/2025 Approved RAUL BARAJAS
PLUMBING-Final 1/28/2025 Approved RAUL BARAJAS