5634-5636 N LEMONA AVE 91411

Certificate Information: 5634-5636 N LEMONA AVE 91411

Application / Permit
24016-10000-01566
Plan Check / Job No.
B24LA00868
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: 1ST AND 2ND STORY MAJOR ADDITION AND REMODEL AND CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 6/5/2024
Issuing Office
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 DANIEL YIP
Corrections Issued 2/3/2024 DANIEL YIP
Quality Review Completed 2/5/2024 PRANITA SHAH
Plan Check Approved 5/31/2024 DANIEL YIP
Issued 6/5/2024 APPLICANT
CofO in Progress 10/16/2025 RYAN SALAZAR
Permit Finaled 11/4/2025 RUBEN SALAS
CofO Issued 11/4/2025 RUBEN SALAS
Permit Finaled 11/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/7/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/8/2024 EDGAR ALCARAZ
Sewer availability Cleared 2/8/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 5/15/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/20/2024 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: NA52361       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/27/2024 Partial Inspection RYAN SALAZAR
Footing/Foundation/Slab 10/17/2024 Approved RYAN SALAZAR
PLUMBING-Rough 10/17/2024 Partial Approval RYAN SALAZAR
Deputy Reinf. Concrete 10/18/2024 Conditional Approval ROBERT GOLD
Deputy Steel/Welding 10/22/2024 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Approval RYAN SALAZAR
Green Building Rough 10/23/2024 Not Ready for Inspection RYAN SALAZAR
Structural Steel Frame 10/23/2024 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 11/4/2024 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 1/28/2025 Conditional Approval RYAN SALAZAR
ELECTRICAL-Rough 1/28/2025 Approved RYAN SALAZAR
Green Building Rough 1/28/2025 Approved RYAN SALAZAR
HVAC-Rough 1/28/2025 Approved RYAN SALAZAR
PLUMBING-Rough 1/28/2025 Approved RYAN SALAZAR
Sewer 1/28/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 1/28/2025 Approved RYAN SALAZAR
Insulation 2/12/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/12/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 2/18/2025 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 2/18/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 2/20/2025 Approved RYAN SALAZAR
Gas Test 4/14/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/29/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
HVAC-Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Not Ready RYAN SALAZAR
Smoke Detectors 5/29/2025 Approved RYAN SALAZAR
Structural Steel Frame 5/29/2025 Approved RYAN SALAZAR
Final 8/26/2025 Partial Inspection RYAN SALAZAR
Green Building Final 8/26/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved RYAN SALAZAR
Final 10/6/2025 OK to Issue CofO RYAN SALAZAR