5634-5636 N LEMONA AVE 91411
Certificate Information: 5634-5636 N LEMONA AVE 91411
- Application / Permit
- 24016-10000-01566
- Plan Check / Job No.
- B24LA00868
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: 1ST AND 2ND STORY MAJOR ADDITION AND REMODEL AND CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | DANIEL YIP |
| Corrections Issued | 2/3/2024 | DANIEL YIP |
| Quality Review Completed | 2/5/2024 | PRANITA SHAH |
| Plan Check Approved | 5/31/2024 | DANIEL YIP |
| Issued | 6/5/2024 | APPLICANT |
| CofO in Progress | 10/16/2025 | RYAN SALAZAR |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
| CofO Issued | 11/4/2025 | RUBEN SALAS |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/8/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 5/15/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | CARLOS AGUILERA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: NA52361 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/27/2024 | Partial Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/17/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/17/2024 | Partial Approval | RYAN SALAZAR |
| Deputy Reinf. Concrete | 10/18/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Steel/Welding | 10/22/2024 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 10/23/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Structural Steel Frame | 10/23/2024 | Conditional Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/4/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/28/2025 | Conditional Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| Sewer | 1/28/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/28/2025 | Approved | RYAN SALAZAR |
| Insulation | 2/12/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/12/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 2/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 2/20/2025 | Approved | RYAN SALAZAR |
| Gas Test | 4/14/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 5/29/2025 | Approved | RYAN SALAZAR |
| Structural Steel Frame | 5/29/2025 | Approved | RYAN SALAZAR |
| Final | 8/26/2025 | Partial Inspection | RYAN SALAZAR |
| Green Building Final | 8/26/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Approved | RYAN SALAZAR |
| Final | 10/6/2025 | OK to Issue CofO | RYAN SALAZAR |