779 N LATIMER ROAD 90402
Certificate Information: 779 N LATIMER ROAD 90402
- Application / Permit
- 24016-10000-01548
- Plan Check / Job No.
- B24LA00853
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ***EPLAN*** MAJOR REMODEL AND ADDITION TO (E) TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE FIRE SPRINKLERED NFPA 13D THROUGH OUT
- Permit Issued
- Issued on 5/2/2025
- Issuing Office
- Current Status
- Issued on 5/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | JAD BASMA |
| Corrections Issued | 2/3/2024 | JAD BASMA |
| Quality Review Completed | 2/6/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 7/5/2024 | JAD BASMA |
| Applicant returned to address corrections | 8/13/2024 | JAD BASMA |
| Applicant returned to address corrections | 9/18/2024 | JAD BASMA |
| Applicant returned to address corrections | 2/25/2025 | JAD BASMA |
| Plan Check Approved | 4/7/2025 | JAD BASMA |
| Issued | 5/2/2025 | APPLICANT |
Permit Application Clearance Information
| Private street | Cleared | 2/20/2024 | DALIA MOKAYED |
| BHO/Hillside ordinance | Cleared | 2/23/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/23/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/23/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/23/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/23/2024 | DINAH GARIN |
| Permit | Cleared | 2/23/2024 | DINAH GARIN |
| Trees in Parkway | Cleared | 2/23/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 3/15/2024 | MATTHEW CRAIG |
| Sewer availability | Cleared | 7/19/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2024 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 2/25/2025 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 2/25/2025 | JAD BASMA |
| Low Impact Development (LID) | Cleared | 3/12/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 3/13/2025 | DIANA RENTERIA |
| Watercourse | Cleared | 4/7/2025 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Dalton Construction; Lic. No.: 447689-B | , |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Wood Frame | 6/8/2026 |
| Interior/Exterior Lathing | 6/9/2026 |
Inspection Request History
| Footing/Foundation/Slab | 6/5/2025 | Not Ready for Inspection | HERBERT GIRON |
| Reinforced Concrete Frame | 6/5/2025 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 6/6/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 7/21/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 8/29/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/23/2025 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 10/3/2025 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/3/2025 | Corrections Issued | HERBERT GIRON |
| Deputy Steel/Welding | 10/6/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 10/8/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Partial Approval | RUBEN RIVAS |
| Footing/Foundation/Slab | 12/15/2025 | Partial Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 4/3/2026 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 4/6/2026 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 4/8/2026 | Approved | HERBERT GIRON |
| Deputy Reinf. Concrete | 4/13/2026 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 4/15/2026 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 4/30/2026 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 5/6/2026 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 5/12/2026 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 6/4/2026 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 6/5/2026 | Approved | HERBERT GIRON |