685 S THAYER AVE 90024
Certificate Information: 685 S THAYER AVE 90024
- Application / Permit
- 24016-10000-01426
- Plan Check / Job No.
- B24LA00770
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) S.F.D WITH ATTACHED GARAGE, REMODEL KITCHEN, BEDROOMS, LIVING ROOM, BATHROOMS AND GARAGE, AND ADDITION OF ATTACHED 8'-3 1/2" x 15'- 0 1/2" TRELLIS PER ENGINEERING.
- Permit Issued
- Issued on 3/22/2024
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | ALFRED RAMIREZ |
| Corrections Issued | 1/20/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/26/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 2/1/2024 | SARKIS HARABEDIAN |
| Plan Check Approved | 2/9/2024 | SARKIS HARABEDIAN |
| Issued | 3/22/2024 | APPLICANT |
| CofO in Progress | 9/3/2025 | DANIEL VERA |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
| CofO Issued | 9/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 1/22/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 1/22/2024 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 1/24/2024 | VASIL MIHALEV |
| Hold | Cleared | 2/6/2024 | MARIA VENDIVIL |
Contact Information
| Architect | Hsu,, Peggy P; Lic. No.: NA32998 | , |
| Contractor | Linework Development And Construction Inc; Lic. No.: 1017174-B | , |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 9/17/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/24/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 9/24/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/24/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/6/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 12/6/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/20/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 1/7/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/14/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Shower Pan | 1/14/2025 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 1/22/2025 | Approved | REGINA MENDEZ |
| Gas Test | 1/22/2025 | Not Ready for Inspection | REGINA MENDEZ |
| Interior/Exterior Lathing | 1/22/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 1/22/2025 | Approved | REGINA MENDEZ |
| Footing/Foundation/Slab | 2/5/2025 | Approved | STEPHANIE SWANSON |
| Gas Test | 4/1/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 8/18/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 8/18/2025 | Approved | DANIEL VERA |
| Final | 8/18/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 8/18/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 8/18/2025 | Approved | DANIEL VERA |
| HVAC-Final | 8/18/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 8/18/2025 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 8/18/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | DANIEL VERA |
| Final | 9/2/2025 | OK to Issue CofO | DANIEL VERA |
| Green Building Final | 9/2/2025 | Approved | DANIEL VERA |
| HVAC-Final | 9/2/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 9/2/2025 | Approved | DANIEL VERA |