469 N ARBRAMAR AVE 90272

Certificate Information: 469 N ARBRAMAR AVE 90272

Application / Permit
24016-10000-01420
Plan Check / Job No.
B24LA00769
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL (E) SFD
Permit Issued
Issued on 3/28/2024
Issuing Office
Current Status
Permit Finaled on 5/14/2026

Permit Application Status History

Submitted 1/16/2024 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 FERNANDO FLORES
Corrections Issued 1/22/2024 FERNANDO FLORES
Plan Check Approved 3/26/2024 FERNANDO FLORES
Issued 3/28/2024 APPLICANT
Permit Finaled 5/15/2026 MEL KHACHATOURIAN

Permit Application Clearance Information

Coastal Zone Cleared 2/22/2024 ALEX VELA

Contact Information

Contractor Voshall Construction Inc; Lic. No.: 920839-B       ,
Engineer Kim,, Taewon; Lic. No.: C80632 28531 PALOS VERDES DR EAST      RANCHO PALOS VERDES, CA 90275

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/10/2024 Approved EVAN COOPER
PLUMBING-Rough 9/10/2024 Not Ready for Inspection EVAN COOPER
Wood Frame 9/10/2024 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 9/26/2024 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 9/26/2024 Corrections Issued EVAN COOPER
HVAC-Rough 9/26/2024 Corrections Issued EVAN COOPER
PLUMBING-Rough 9/26/2024 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 10/11/2024 Approved EVAN COOPER
Insulation 10/11/2024 Approved EVAN COOPER
ELECTRICAL-Rough 10/17/2024 Approved EVAN COOPER
HVAC-Rough 10/17/2024 Approved EVAN COOPER
PLUMBING-Rough 10/17/2024 Approved EVAN COOPER
Drywall Nailing 10/29/2024 Approved EVAN COOPER
Shower Pan 11/15/2024 Approved EVAN COOPER
Interior/Exterior Lathing 2/19/2025 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Final 4/7/2026 Approved MEL KHACHATOURIAN
HVAC-Final 4/7/2026 Conditional Approval MEL KHACHATOURIAN
PLUMBING-Final 4/7/2026 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Final 4/15/2026 Approved MEL KHACHATOURIAN
HVAC-Final 4/15/2026 Conditional Approval MEL KHACHATOURIAN
PLUMBING-Final 4/15/2026 Approved MEL KHACHATOURIAN
Final 5/15/2026 Permit Finaled MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 5/15/2026 Approved MEL KHACHATOURIAN