6344 1/2 W LEXINGTON AVE 90038

Certificate Information: 6344 1/2 W LEXINGTON AVE 90038

Application / Permit
24016-10000-01364
Plan Check / Job No.
B24LA00731
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) 18' x 9' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). WORK DONE PER WFPP.
Permit Issued
Issued on 2/6/2024
Issuing Office
Current Status
CofO Issued on 4/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2024 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 DANIEL ABRAMYAN
Corrections Issued 1/19/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 2/1/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 2/5/2024 MIROOSH KHACHATOORIAN
Issued 2/6/2024 APPLICANT
CofO in Progress 4/22/2025 CRAIG VAUGHAN
Permit Finaled 4/23/2025 DEROLD HAUFF
CofO Issued 4/23/2025 DEROLD HAUFF
Permit Finaled 4/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/25/2024 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 1/25/2024 ARNULFO CHAMU
Sewer availability Cleared 1/25/2024 ARNULFO CHAMU

Contact Information

Contractor Salcido Mac Donald Jr; Lic. No.: 929472-B       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/21/2024 Not Ready for Inspection ROY SPAULDING
HVAC-Rough 2/21/2024 Not Ready for Inspection ROY SPAULDING
Interior/Exterior Lathing 2/21/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 2/21/2024 Not Ready for Inspection ROY SPAULDING
Shower Pan 2/21/2024 Not Ready for Inspection ROY SPAULDING
Sewer 2/26/2024 Approved ROY SPAULDING
PLUMBING-Rough 4/4/2024 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 4/17/2024 Approved ROY SPAULDING
Deputy Drilled-In Anchors 6/17/2024 Conditional Approval ROY SPAULDING
ELECTRICAL-Rough 7/9/2024 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Approval BRIAN SULLIVAN
HVAC-Rough 7/9/2024 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 7/9/2024 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 7/9/2024 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 7/15/2024 Approved ROY SPAULDING
PLUMBING-Rough 7/15/2024 Approved ROY SPAULDING
Wood Frame 7/15/2024 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 7/23/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 7/23/2024 Approved ROY SPAULDING
HVAC-Rough 7/23/2024 Approved ROY SPAULDING
PLUMBING-Rough 7/23/2024 Approved ROY SPAULDING
Shower Pan 7/23/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 7/26/2024 Not Ready for Inspection ROY SPAULDING
Insulation 8/19/2024 Not Ready for Inspection ROY SPAULDING
Interior/Exterior Lathing 8/19/2024 Not Ready for Inspection ROY SPAULDING
Insulation 9/3/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/3/2024 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/10/2024 Approved CRAIG VAUGHAN
Drywall Nailing 9/16/2024 Approved CRAIG VAUGHAN
Shower Pan 9/16/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Not Ready CRAIG VAUGHAN
Final 11/21/2024 Partial Approval CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 11/21/2024 Approved CRAIG VAUGHAN
Final 12/17/2024 Corrections Issued CRAIG VAUGHAN
Final 2/3/2025 Corrections Issued WILLIAM SIERRA
Final 3/27/2025 Corrections Issued CRAIG VAUGHAN
Final 4/17/2025 OK to Issue CofO CRAIG VAUGHAN
Pre-Inspection 4/17/2025 Approved CRAIG VAUGHAN