1930 S WESTHOLME AVE 90025

Certificate Information: 1930 S WESTHOLME AVE 90025

Application / Permit
24016-10000-01337
Plan Check / Job No.
B24LA00700
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EXISTING 1-STORY SFD INCLUDING (N) WINDOWS, RE-ROOF, REPLACE (E) REAR PATIO ROOF WITH NEW TRELLIS
Permit Issued
Issued on 2/14/2024
Issuing Office
Valley
Current Status
Permit Finaled on 3/14/2025

Permit Application Status History

Submitted 1/16/2024 APPLICANT
Assigned to Plan Check Engineer 1/16/2024 SAMUEL GONZALEZ
Corrections Issued 1/16/2024 SAMUEL GONZALEZ
Plan Check Approved 2/9/2024 MINA HABILI
Issued 2/14/2024 APPLICANT
Permit Finaled 3/13/2025 DANIEL VERA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/1/2024 VASIL MIHALEV

Contact Information

Architect Moffitt,, Gina Gilbert; Lic. No.: C12330 620 MOULTON AVENUE STUDIO # 106      LOS ANGELES, CA 90031
Contractor Prestige Contracting; Lic. No.: 543415-B P O BOX 775      ACTON, CA 93510
Engineer Nastarin,, Hooman; Lic. No.: C62199 554 S SAN VICNETE BLVD 202      LOS ANGELES, CA 90048

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/30/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/7/2024 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 7/2/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 7/2/2024 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 7/2/2024 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 7/2/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/17/2024 Conditional Approval STEPHANIE SWANSON
Special/Order Compliance 7/17/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/23/2024 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 7/23/2024 Approved STEPHANIE SWANSON
HVAC-Rough 7/23/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 7/26/2024 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 7/26/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 8/1/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 8/1/2024 Partial Approval STEPHANIE SWANSON
Insulation 8/2/2024 Approved STEPHANIE SWANSON
Drywall Nailing 8/12/2024 Approved STEPHANIE SWANSON
Final 8/12/2024 Corrections Issued STEPHANIE SWANSON
Final 3/10/2025 Corrections Issued DANIEL VERA
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Not Ready DANIEL VERA
Smoke Detectors 3/10/2025 Approved DANIEL VERA
Final 3/13/2025 Permit Finaled DANIEL VERA
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Approved DANIEL VERA