3115 S GILMERTON AVE 90064

Certificate Information: 3115 S GILMERTON AVE 90064

Application / Permit
24016-10000-01156
Plan Check / Job No.
B24LA00626
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
****ePlan**** Convert (e) detached 2-car garage at rear of the lot to an ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/20/2024
Issuing Office
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2024 APPLICANT
Assigned to Plan Check Engineer 1/18/2024 REZA HAGHIGHAT
Corrections Issued 1/21/2024 REZA HAGHIGHAT
Quality Review Completed 1/30/2024 KAVIAN REFAHI
Plan Check Approved 3/17/2024 REZA HAGHIGHAT
Issued 3/20/2024 APPLICANT
CofO in Progress 12/13/2024 BOBBY KEY
Permit Finaled 12/24/2024 RICHARD STEINBACH
CofO Issued 12/24/2024 RICHARD STEINBACH
Permit Finaled 12/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/29/2024 LIAM ODONOVAN
Sewer availability Cleared 1/29/2024 LIAM ODONOVAN
Specific Plan Cleared 1/29/2024 ALESSANDRO MERCURI
Eng Process Fee Ord 176,300 Cleared 2/1/2024 LIAM ODONOVAN
Grading Pre-Inspection Cleared 3/17/2024 REZA HAGHIGHAT

Contact Information

Contractor Concept Renovations Inc; Lic. No.: 1016942-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/7/2024 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 6/11/2024 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 6/11/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Rough 6/11/2024 Not Ready for Inspection TEMISTOCLES CAAL
MERV13>=Rough 6/11/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 6/11/2024 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 6/11/2024 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 6/26/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/26/2024 Approved CARLOS MATAMOROS
Underground Mechanical 6/26/2024 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 7/15/2024 Corrections Issued KEVIN SARGSYAN
Green Building Rough 7/15/2024 Approved KEVIN SARGSYAN
HVAC-Rough 7/15/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/15/2024 Partial Approval KEVIN SARGSYAN
MERV13>=Rough 7/15/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/22/2024 Partial Approval ASHLEY THOMPSON
Shower Pan 7/22/2024 Approved ASHLEY THOMPSON
Insulation 7/29/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 7/29/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 8/7/2024 Partial Approval ASHLEY THOMPSON
Insulation 8/7/2024 Approved ASHLEY THOMPSON
PLUMBING-Rough 8/7/2024 Corrections Issued ASHLEY THOMPSON
Underground Mechanical 8/7/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 8/15/2024 Partial Approval KIRK SANDERS
Special/Order Compliance 8/15/2024 Corrections Issued KIRK SANDERS
Drywall Nailing 8/23/2024 Approved REGINA MENDEZ
Pre-Inspection 8/30/2024 Approved REGINA MENDEZ
BUILDING-Rough-Frame 11/22/2024 Approved ASHLEY THOMPSON
Final 11/22/2024 Corrections Issued ASHLEY THOMPSON
Green Building Final 11/22/2024 Approved ASHLEY THOMPSON
MERV13>=Final 11/22/2024 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 11/22/2024 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Ready ASHLEY THOMPSON
Final 12/4/2024 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 12/4/2024 Approved ASHLEY THOMPSON
Final 12/9/2024 Partial Inspection STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Not Ready STEPHANIE SWANSON
Final 12/13/2024 OK to Issue CofO BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/13/2024 SGSOV Approved BOBBY KEY
Service/Power Release 12/13/2024 Approved BOBBY KEY