6018-6022 W BARTON AVE 90038
Certificate Information: 6018-6022 W BARTON AVE 90038
- Application / Permit
- 24016-10000-01074
- Plan Check / Job No.
- B24LA00585
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- *EPLAN* CONVERT PORTION OF (E) ATTACHED CARPORT WITHIN (E) 3-STORY APARTMENT TO ACCESSORY DWELLING UNIT PER CA 65852.2(e)(1)(C) AND OTHER PORTION TO STORAGE AREA (231 SF).
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Current Status
- CofO Issued on 7/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | VIVIAN LAO |
| Assigned to Zoning Architect | 2/1/2024 | CALEB WONG |
| Corrections Issued | 2/8/2024 | VIVIAN LAO |
| Quality Review Completed | 2/8/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 7/10/2024 | VIVIAN LAO |
| Plan Check Approved | 7/17/2024 | VIVIAN LAO |
| Issued | 8/6/2024 | APPLICANT |
| Permit Finaled | 7/14/2026 | DAVID BURKHEAD |
| CofO Issued | 7/14/2026 | DAVID BURKHEAD |
| Permit Finaled | 7/14/2026 | DAVID BURKHEAD |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2024 | KENIA CASTILLO |
| Sewer availability | Cleared | 5/24/2024 | KENIA CASTILLO |
| ZI | Cleared | 6/13/2024 | DAVID URITA |
| Green Code | Cleared | 6/25/2024 | Rosendo Medina |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | KENIA CASTILLO |
| Zoning Plan Check | Cleared | 6/28/2024 | Rosendo Medina |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/19/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Pre-Inspection | 8/23/2024 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 11/27/2024 | Partial Inspection | TIMOTHY POWELL |
| Drywall Nailing | 6/15/2026 | Approved | CHRISTOPHER BLACKWOOD |
| Final | 6/15/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Green Building Final | 6/15/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Green Building Rough | 6/15/2026 | Approved | CHRISTOPHER BLACKWOOD |
| METHANE-Final | 6/15/2026 | Approved | CHRISTOPHER BLACKWOOD |
| METHANE-Rough | 6/15/2026 | Approved | CHRISTOPHER BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 6/15/2026 | SGSOV No Gas | CHRISTOPHER BLACKWOOD |
| Smoke Detectors | 6/15/2026 | Approved | CHRISTOPHER BLACKWOOD |
| Wood Frame | 6/15/2026 | Approved | CHRISTOPHER BLACKWOOD |
| Final | 7/6/2026 | Conditional Approval | CHRISTOPHER BLACKWOOD |
| Green Building Final | 7/6/2026 | Approved | CHRISTOPHER BLACKWOOD |