1271 N OZETA TER 90069

Certificate Information: 1271 N OZETA TER 90069

Application / Permit
24016-10000-01071
Plan Check / Job No.
B23LA24742
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADD NEW VAULTED AREA PER DESIGN
Permit Issued
Issued on 6/3/2024
Issuing Office
Current Status
Issued on 6/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/12/2024 APPLICANT
Assigned to Plan Check Engineer 1/17/2024 MOHAMMAD ESMAILI
Corrections Issued 1/18/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/6/2024 ALFRED RAMIREZ
Plan Check Approved 4/5/2024 ALEC MOUSAKHANIAN
Issued 6/3/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/21/2024 LANNY MERRICK

Contact Information

Architect O'Herlihy,, Lorcan Patrick; Lic. No.: C24245 4106 W JEFFERSON BLVD      LOS ANGELES, CA 90016
Contractor Manchen Construction Inc ; Lic. No.: 1043435-B       ,
Contractor Manchen Construction Inc; Lic. No.: 1043435-B       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/10/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 7/25/2024 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/29/2024 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Corrections Issued RAUL BARAJAS
Deputy Steel/Welding 9/20/2024 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 10/8/2024 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Rough 10/8/2024 Partial Approval WILLIAM SIERRA
Green Building Rough 10/8/2024 Not Ready for Inspection WILLIAM SIERRA
PLUMBING-Rough 10/8/2024 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 11/4/2024 Approved RAUL BARAJAS
Green Building Rough 11/4/2024 Approved RAUL BARAJAS
HVAC-Rough 11/4/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/4/2024 Partial Approval RAUL BARAJAS
Insulation 11/8/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/22/2024 Approved RAUL BARAJAS
Shower Pan 11/22/2024 Approved RAUL BARAJAS
Drywall Nailing 12/3/2024 Approved CRAIG VAUGHAN
Final 4/8/2025 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/8/2025 Approved CRAIG VAUGHAN
Green Building Final 4/8/2025 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/8/2025 Approved CRAIG VAUGHAN