1031 1/2 S CALZONA ST 90023
Certificate Information: 1031 1/2 S CALZONA ST 90023
- Application / Permit
- 24016-10000-00919
- Plan Check / Job No.
- B24LA00492
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/21/2024
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2024 | SHANGQIN XIE |
| Corrections Issued | 1/18/2024 | SHANGQIN XIE |
| Plan Check Approved | 2/7/2024 | SHANGQIN XIE |
| Issued | 4/21/2024 | APPLICANT |
| CofO in Progress | 10/23/2024 | FREDDIE RIVERA |
| CofO Issued | 10/28/2024 | RUBEN SALAS |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/23/2024 | WALLIE JONG |
| Clean Up Green Up | Cleared | 1/23/2024 | YINGSHI HUANG |
| Sewer availability | Cleared | 1/23/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2024 | WALLIE JONG |
Contact Information
| Contractor | Vaisman Construction Inc; Lic. No.: 1076712-B | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/24/2024 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/29/2024 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 6/24/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/19/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/19/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 7/19/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| MERV13>=Rough | 7/19/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/19/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 7/19/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/23/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/23/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/23/2024 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/23/2024 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 7/23/2024 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 7/23/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/14/2024 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 8/14/2024 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 8/14/2024 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/22/2024 | Partial Approval | JUSTIN HAWLEY |
| Wood Frame | 8/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| Deputy Wood Construction | 8/26/2024 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/3/2024 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 9/3/2024 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/12/2024 | Partial Inspection | FREDDIE RIVERA |
| Drywall Nailing | 9/12/2024 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/12/2024 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 9/12/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/13/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/13/2024 | Approved | FREDDIE RIVERA |
| Final | 10/17/2024 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Final | 10/17/2024 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 10/17/2024 | Approved | FREDDIE RIVERA |
| Final | 10/22/2024 | OK to Issue CofO | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | FREDDIE RIVERA |