Convert (E) detached garage to ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/21/2024
Issuing Office
Current Status
CofO Issued on 10/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2024 APPLICANT
Assigned to Plan Check Engineer 1/17/2024 SHANGQIN XIE
Corrections Issued 1/18/2024 SHANGQIN XIE
Plan Check Approved 2/7/2024 SHANGQIN XIE
Issued 4/21/2024 APPLICANT
CofO in Progress 10/23/2024 FREDDIE RIVERA
CofO Issued 10/28/2024 RUBEN SALAS
Permit Finaled 10/28/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/23/2024 WALLIE JONG
Clean Up Green Up Cleared 1/23/2024 YINGSHI HUANG
Sewer availability Cleared 1/23/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/26/2024 WALLIE JONG

Contact Information

Contractor Vaisman Construction Inc; Lic. No.: 1076712-B       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/29/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 5/24/2024 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 5/29/2024 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 6/24/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 7/19/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 7/19/2024 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 7/19/2024 Not Ready for Inspection JOSEPH MCGARRY
MERV13>=Rough 7/19/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/19/2024 Approved JOSEPH MCGARRY
Shower Pan 7/19/2024 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 7/23/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 7/23/2024 Approved JOSEPH MCGARRY
HVAC-Rough 7/23/2024 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 7/23/2024 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 7/23/2024 Partial Approval JOSEPH MCGARRY
Shower Pan 7/23/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/14/2024 Partial Inspection FREDDIE RIVERA
HVAC-Rough 8/14/2024 Partial Inspection FREDDIE RIVERA
Insulation 8/14/2024 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 8/22/2024 Partial Approval JUSTIN HAWLEY
Wood Frame 8/23/2024 Not Ready for Inspection LUIS CASTRO
Deputy Wood Construction 8/26/2024 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 9/3/2024 Partial Inspection FREDDIE RIVERA
Wood Frame 9/3/2024 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 9/12/2024 Partial Inspection FREDDIE RIVERA
Drywall Nailing 9/12/2024 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 9/12/2024 Partial Inspection FREDDIE RIVERA
Wood Frame 9/12/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/13/2024 Approved FREDDIE RIVERA
Drywall Nailing 9/13/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/13/2024 Approved FREDDIE RIVERA
Final 10/17/2024 Corrections Issued FREDDIE RIVERA
MERV13>=Final 10/17/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 10/17/2024 Approved FREDDIE RIVERA
Final 10/22/2024 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved FREDDIE RIVERA