20431-20433 W ACRE ST 91306

Certificate Information: 20431-20433 W ACRE ST 91306

Application / Permit
24016-10000-00908
Plan Check / Job No.
B24LA00485
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage in single-family dwelling to JADU.per state law CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 7/24/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2024 APPLICANT
Assigned to Plan Check Engineer 1/10/2024 DANIEL SMILEY
Corrections Issued 1/10/2024 DANIEL SMILEY
Applicant returned to address corrections 7/11/2024 SHANGQIN XIE
Plan Check Approved 7/19/2024 YAQUB MIRZA
Issued 7/24/2024 APPLICANT
CofO in Progress 11/22/2024 JEFFREY HARTLINE
Permit Finaled 12/11/2024 JOHN JANSON
CofO Issued 12/11/2024 JOHN JANSON
Permit Finaled 12/11/2024 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 7/7/2024 RIDWAN HARDY
Construction within easement Cleared 7/7/2024 RIDWAN HARDY
Address approval Cleared 7/18/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/19/2024 CARLOS AGUILERA
Sewer availability Cleared 7/19/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/7/2024 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 8/13/2024 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/13/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/22/2024 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/5/2024 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/5/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 9/5/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 9/5/2024 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 9/5/2024 Corrections Issued CHRIS CHRISTENSEN
Special/Order Compliance 9/5/2024 Approved SCOTT SOBEL
Wood Frame 9/5/2024 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/9/2024 Approved CHRIS CHRISTENSEN
HVAC-Rough 9/9/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/9/2024 Approved CHRIS CHRISTENSEN
Wood Frame 9/9/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/17/2024 Approved ARUTYUN MADATYAN
Green Building Rough 9/17/2024 Approved ARUTYUN MADATYAN
Insulation 9/17/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 9/17/2024 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 9/25/2024 Approved CHRIS CHRISTENSEN
Gas Test 9/25/2024 Approved CHRIS CHRISTENSEN
Underground Mechanical 9/25/2024 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 11/8/2024 Partial Approval JEFFREY HARTLINE
Final 11/15/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 11/15/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 11/15/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 11/21/2024 Approved JEFFREY HARTLINE
Final 11/21/2024 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 11/21/2024 Approved JEFFREY HARTLINE
PLUMBING-Final 11/21/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 11/21/2024 Approved JEFFREY HARTLINE
Smoke Detectors 11/21/2024 Approved JEFFREY HARTLINE