913 S MALCOLM AVE 90024
Certificate Information: 913 S MALCOLM AVE 90024
- Application / Permit
- 24016-10000-00893
- Plan Check / Job No.
- B24LA00475
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 2-STORY ALQ ROOM AND GARAGE WITH STORAGE INTO A.D.U. PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/13/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/19/2024 | APPLICANT |
| Applicant returned to address corrections | 1/25/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 2/27/2024 | CRISTINA SALAZAR |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 1/17/2025 | CHRISTOPHER WILSON |
| CofO Issued | 1/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/14/2024 | PEDRO AYALA |
| Address approval | Cleared | 2/15/2024 | DARIN LAM |
| Sewer availability | Cleared | 2/15/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2024 | DARIN LAM |
Contact Information
| Architect | Maly,, Farzin; Lic. No.: C33731 | 7136 HASKELL AVENUE # 320 VAN NUYS, CA 91406 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/29/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 2/29/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 2/29/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 2/29/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 2/29/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/15/2024 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/15/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/15/2024 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Elec/Plmb/HVAC | 3/15/2024 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 3/15/2024 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 4/2/2024 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/2/2024 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/5/2024 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 4/5/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 4/5/2024 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/5/2024 | Approved | CHRISTOPHER WILSON |
| Wood Frame | 4/5/2024 | Approved | CHRISTOPHER WILSON |
| Final | 12/6/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 12/6/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 12/6/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 12/23/2024 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 12/23/2024 | Approved | CHRISTOPHER WILSON |
| Final | 1/16/2025 | OK to Issue CofO | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 1/16/2025 | Approved | CHRISTOPHER WILSON |