4336 S LYCEUM AVE 90066
Certificate Information: 4336 S LYCEUM AVE 90066
- Application / Permit
- 24016-10000-00858
- Plan Check / Job No.
- B24LA00457
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: REMODEL TO (E) SFD TO REVISE LAYOUT TO CREATE (N) MASTER BEDROOM/BATHROOM, NURSERY ROOM, AND KITCHEN. ADD NEW WINDOW, DOOR, AND SKYLIGHT PER PLAN. ALL WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 11/4/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/8/2025
Permit Application Status History
| Submitted | 2/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2024 | OMAR GARNICA |
| Plan Check Approved | 2/20/2024 | OMAR GARNICA |
| Issued | 11/4/2024 | APPLICANT |
| Permit Finaled | 5/7/2025 | TEMISTOCLES CAAL |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Construxx; Lic. No.: 950847-B | , |
| Contractor | Y & S Construction Inc; Lic. No.: 950847-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: NA87698 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/31/2024 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 1/7/2025 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 1/7/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 1/7/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 1/7/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 1/24/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 1/24/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 1/30/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 1/30/2025 | Approved | JESUS PINEDA |
| Shower Pan | 1/30/2025 | Approved | JESUS PINEDA |
| Insulation | 2/5/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/5/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 2/7/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/18/2025 | No Access for Inspection | MICHAEL ALLEN |
| Final | 4/18/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 4/18/2025 | Conditional Approval | MICHAEL ALLEN |
| PLUMBING-Final | 4/18/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 4/18/2025 | Approved | MICHAEL ALLEN |
| Final | 5/7/2025 | Permit Finaled | TEMISTOCLES CAAL |