5249 W CENTURY BLVD 90045

Certificate Information: 5249 W CENTURY BLVD 90045

Application / Permit
24016-10000-00852
Plan Check / Job No.
B24LA00452
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
(eplan) Remodel of existing Hotel. Work to include updating first floor Public space, infilling the public swimming pool, adding storefront glazing, and upgrading 26 ADA guestrooms. Work to include new openings on the exterior walls, new masonry shear walls, new partitions, ceiling, doors, fixtures, and finishes. No change of use. <Under separate permit for remodeling the kitchen, restaurant bar, and buffet area>
Permit Issued
Issued on 5/13/2024
Issuing Office
Current Status
Permit Finaled on 7/25/2025

Permit Application Status History

Submitted 1/12/2024 APPLICANT
Assigned to Plan Check Engineer 1/18/2024 YOUNG KIM
Assigned to Zoning Architect 1/18/2024 YOUNG KIM
Corrections Issued 1/25/2024 YOUNG KIM
Quality Review Completed 2/6/2024 GARO TELMI
Applicant returned to address corrections 4/12/2024 YOUNG KIM
Applicant returned to address corrections 4/15/2024 YOUNG KIM
Applicant returned to address corrections 4/23/2024 YOUNG KIM
Plan Check Approved 5/4/2024 YOUNG KIM
Issued 5/13/2024 APPLICANT
Permit Finaled 7/25/2025 RICARDO ROBLES

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 3/11/2024 ANDREW KO
Community Plan Implem. Overlay Cleared 3/14/2024 CAELAN RAFFERTY
DAS Clearance Cleared 4/5/2024 Samuel Gonzalez
Green Code Cleared 4/5/2024 Samuel Gonzalez
Zoning Plan Check Cleared 4/14/2024 Samuel Gonzalez

Contact Information

Architect Fong,, Gene L; Lic. No.: C9063 375 N BONHILL RD      LOS ANGELES, CA 90049
Contractor National Lodging Renovation Management Inc; Lic. No.: 1070494-B 3277 E WARM SPRINGS DRIVE #300      LAS VEGAS, NV 89120
Engineer Chamberlain,, Craig Morgan; Lic. No.: S4588 1517 23RD ST      MANHATTAN BEACH, CA 90266

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 6/18/2024 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 6/18/2024 Partial Approval GRANT WOODS
Light Gage Steel Frame 6/27/2024 Partial Approval GRANT WOODS
Insulation 7/3/2024 Approved DERRICK SPENCER
Light Gage Steel Frame 7/3/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 7/12/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 7/23/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 7/23/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 7/31/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 8/8/2024 Approved RICARDO ROBLES
Light Gage Steel Frame 8/12/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 8/20/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 8/20/2024 Partial Approval RICARDO ROBLES
Deputy Reinf. Concrete 8/27/2024 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 8/28/2024 Partial Approval RICARDO ROBLES
Footing/Foundation/Slab 9/10/2024 Partial Approval GRANT WOODS
Reinforced Masonry Frame 9/10/2024 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 9/11/2024 Conditional Approval GRANT WOODS
Masonry Wall/Backfill 9/23/2024 Not Ready for Inspection GRANT WOODS
Masonry Wall/Backfill 9/24/2024 Not Ready for Inspection GRANT WOODS
Drywall Nailing 9/25/2024 No Access for Inspection MICHAEL PETRUSKO
Drywall Nailing 10/1/2024 Partial Approval GRANT WOODS
Insulation 10/1/2024 Partial Approval GRANT WOODS
Light Gage Steel Frame 10/1/2024 Partial Approval GRANT WOODS
Drywall Nailing 10/16/2024 Partial Approval GRANT WOODS
Light Gage Steel Frame 10/16/2024 Not Ready for Inspection GRANT WOODS
Smoke Detectors 10/16/2024 Not Ready for Inspection GRANT WOODS
Drywall Nailing 10/22/2024 Approved MICHAEL PETRUSKO
Light Gage Steel Frame 10/23/2024 Approved MICHAEL PETRUSKO
Deputy Reinf. Concrete 10/30/2024 Conditional Approval GRANT WOODS
Smoke Detectors 10/30/2024 Not Ready for Inspection MICHAEL PETRUSKO
Drywall Nailing 11/12/2024 Partial Approval RICARDO ROBLES
Insulation 11/12/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 12/30/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 1/3/2025 Partial Approval GRANT WOODS
Light Gage Steel Frame 1/3/2025 Corrections Issued GRANT WOODS
Final 1/22/2025 Partial Approval JOEY BUCHANAN
Green Building Final 1/22/2025 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 1/22/2025 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Inspection RICARDO ROBLES
Light Gage Steel Frame 2/19/2025 Partial Inspection RICARDO ROBLES
Light Gage Steel Frame 2/20/2025 Approved MICHAEL PETRUSKO
Drywall Nailing 3/5/2025 Partial Approval RICARDO ROBLES
Structural Steel Frame 4/14/2025 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 4/29/2025 Approved RICARDO ROBLES
Final 6/25/2025 Partial Approval DERRICK SPENCER
Special/Order Compliance 6/25/2025 Approved DERRICK SPENCER
Final 7/25/2025 Permit Finaled RICARDO ROBLES