2819 3/4 E FOLSOM ST 90033

Certificate Information: 2819 3/4 E FOLSOM ST 90033

Application / Permit
24016-10000-00693
Plan Check / Job No.
B24LA00361
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Convert Part of (E) Apartment Unit to (778sq.ft) ADU per LAMC 12.22 A.33(c) AND (e). NO CHANGE IN FOOTPRINT AND ALL THE DOORS AND WINDOWS. NO STRUCTURAL WORK.
Permit Issued
Issued on 2/21/2024
Issuing Office
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2024 APPLICANT
Assigned to Plan Check Engineer 1/16/2024 DAVID CASTILLO
Corrections Issued 1/17/2024 DAVID CASTILLO
Plan Check Approved 1/26/2024 DAVID CASTILLO
Issued 2/21/2024 APPLICANT
CofO in Progress 9/10/2024 RONALD JIMENEZ
Permit Finaled 9/10/2024 ERNESTO CORRAL
CofO Issued 9/10/2024 ERNESTO CORRAL
Permit Finaled 9/10/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/19/2024 DAVID VO
Sewer availability Cleared 1/19/2024 DAVID VO
Eng Process Fee Ord 176,300 Cleared 1/23/2024 CHRISTINA BRACO

Contact Information

Contractor Sharp Builders & Son; Lic. No.: 1058253-B       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/22/2024 Approved RONALD JIMENEZ
Drywall Nailing 4/1/2024 Partial Approval RONALD JIMENEZ
Insulation 5/6/2024 Approved RAMAZANALI ALMASI
Drywall Nailing 5/8/2024 Approved RONALD JIMENEZ
Final 6/25/2024 Corrections Issued RONALD JIMENEZ
METHANE-Final 6/25/2024 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Not Ready RONALD JIMENEZ
Smoke Detectors 6/25/2024 Approved RONALD JIMENEZ
Final 7/17/2024 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/17/2024 SGSOV Not Ready RONALD JIMENEZ
Final 7/22/2024 Conditional Approval RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved RONALD JIMENEZ
Pre-Inspection 8/20/2024 Not Ready for Inspection LUIS CCAMACHO
Final 9/10/2024 OK to Issue CofO RONALD JIMENEZ