1403 N SEWARD ST #4 90028
Certificate Information: 1403 N SEWARD ST #4 90028
- Application / Permit
- 24016-10000-00653
- Plan Check / Job No.
- B24LA00344
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (2) Duplex
- Work Description
- EPLAN Attached garage conversion at an existing 2-story Duplex building into an Accessory Dwelling Unit per GC 66323(a)(3)
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- Issued on 6/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | PRANITA SHAH |
| Assigned to Zoning Architect | 1/11/2024 | PRANITA SHAH |
| Corrections Issued | 1/26/2024 | PRANITA SHAH |
| Quality Review Completed | 2/5/2024 | GARO TELMI |
| Applicant returned to address corrections | 3/19/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 4/24/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 5/9/2024 | PRANITA SHAH |
| Plan Check Approved | 4/14/2025 | PRANITA SHAH |
| Issued | 6/4/2025 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 2/8/2024 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2024 | CHRISTINA BRACO |
| Address approval | Cleared | 6/18/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 6/27/2024 | CHRISTINA BRACO |
| Tenant Habitability Plan | Cleared | 9/5/2024 | HUGO GARRIDO GARZA |
| Redevelopment Project Area | Cleared | 2/6/2025 | YASMINE BASHIRI |
| ZI | Cleared | 2/10/2025 | YASMINE BASHIRI |
| DAS Clearance | Cleared | 2/27/2025 | Shangqin Xie |
| Zoning Plan Check | Cleared | 3/27/2025 | Shangqin Xie |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: NA93049 | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/8/2025 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 8/8/2025 | Approved | TIMOTHY POWELL |
| Green Building Rough | 8/28/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 8/28/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 10/17/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 10/17/2025 | Partial Inspection | TIMOTHY POWELL |
| Green Building Rough | 10/22/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 10/22/2025 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 11/3/2025 | Approved | TIMOTHY POWELL |
| Insulation | 11/3/2025 | Approved | TIMOTHY POWELL |
| Interior/Exterior Lathing | 11/3/2025 | Approved | TIMOTHY POWELL |
| Final | 7/6/2026 | Conditional Approval | CHRISTOPHER BLACKWOOD |
| Green Building Final | 7/6/2026 | Approved | CHRISTOPHER BLACKWOOD |
| Green Building Rough | 7/6/2026 | Approved | CHRISTOPHER BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 7/6/2026 | SGSOV Approved | CHRISTOPHER BLACKWOOD |
| Smoke Detectors | 7/6/2026 | Approved | CHRISTOPHER BLACKWOOD |
| Wood Frame | 7/6/2026 | Approved | CHRISTOPHER BLACKWOOD |