635 S WESTERN AVE 90005
Certificate Information: 635 S WESTERN AVE 90005
- Application / Permit
- 24016-10000-00591
- Plan Check / Job No.
- B23LA24705
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Parking Building
- Work Description
- ePlan. New parking elevator pit at existing parking structure
- Permit Issued
- Issued on 7/25/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/18/2026
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | PRANITA SHAH |
| Corrections Issued | 1/30/2024 | PRANITA SHAH |
| Quality Review Completed | 2/14/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 4/30/2024 | PRANITA SHAH |
| Plan Check Approved | 7/24/2024 | PRANITA SHAH |
| Issued | 7/25/2024 | APPLICANT |
| Permit Finaled | 2/18/2026 | MARTIN TAVITIAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/23/2024 | DANIEL CORONADO |
| "T" removal | Cleared | 2/23/2024 | DANIEL CORONADO |
| Redevelopment Project Area | Cleared | 3/20/2024 | ELIZABETH GALLARDO |
| Fire Marshal Fire Life Safety | Cleared | 5/8/2024 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 7/10/2024 | Lawrence Quirante |
Contact Information
| Architect | Melzer,, Mark Henry; Lic. No.: C17918 | 9511 IRVINE CENTER DRIVE IRVINE, CA 92618 |
| Contractor | Philmont Management Inc; Lic. No.: 808686-B | , |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2024 | Partial Approval | JEROME BLACKWOOD |
| Reinforced Concrete Frame | 12/26/2024 | Partial Approval | MARTIN TAVITIAN |
| Reinforced Concrete Frame | 1/2/2025 | Partial Approval | MARTIN TAVITIAN |
| Structural Steel Frame | 6/13/2025 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 6/25/2025 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 6/30/2025 | Partial Approval | MARTIN TAVITIAN |
| Structural Steel Frame | 6/30/2025 | Partial Approval | MARTIN TAVITIAN |
| Reinforced Concrete Frame | 7/11/2025 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 7/16/2025 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 8/13/2025 | Partial Approval | MARTIN TAVITIAN |
| Final | 2/9/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Smoke Detectors | 2/9/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 2/18/2026 | Permit Finaled | MARTIN TAVITIAN |
| Smoke Detectors | 2/18/2026 | Approved | MARTIN TAVITIAN |